Table 1 — Component Cost Detail

ComponentConst. LowConst. HighSvc LifeO&M% LowAnn O&M LowAnn O&M HighRepl. Cost Low (current $)Repl. Cost High (current $)# ReplRepl. at Time of Replacement LowRepl. at Time of Replacement HighPV Repl LowPV Repl HighPV O&M LowPV O&M High
Detention$120,000$180,00010000.005%$6$450$120,000$180,0000$0$0$0$0$113$8,488
Pump Station, Intermittent$40,000$60,000200.500%$200$1,800$40,000$60,0001$65,545$98,317$34,240$51,360$3,772$33,951
Piping, Force Main$15,000$25,000300.500%$75$375$15,000$25,0000$0$0$0$0$1,415$7,073

Replacement costs. A replacement cost is entered as the current cost (today's dollars, a present value); a blank replacement cost uses the construction cost. The cost at the time of each replacement (future value) is estimated with the inflation rate (2.5%): FV = Replacement Cost × (1 + inflation)k × Life, for replacements k = 1, 2, … that fall before the end of the 30-year analysis period (a component whose life is equal to or longer than the period is not replaced). Each future value is discounted to today with the discount rate (3.3%): PV = FV / (1 + discount)k × Life. PV of Replacement is the sum of those present values.

Table 2 — Routine Annual Costs

DescriptionQtyUnitAnnual LowAnnual HighPV LowPV High
Mowing / Vegetation Control / Litter Removal4each$7,400$7,400$139,577$139,577
Stormwater Resale3.1MGY($3,100)($3,100)($58,471)($58,471)

Section D — Electrical Energy

Annual consumption (kWh/yr)6,000
Rate ($/kWh)0.115
Annual electrical cost$690
PV of electrical cost$13,015

Table 3 — Summary

Low EstimateHigh Estimate
Construction Cost$175,000$265,000
PV of Replacement$34,240$51,360
PV of O&M$99,420$143,632
Total PV (Present Worth)$308,660$459,992
Annualized PV (/yr)$16,364$24,388
$/lb TN removed$318.39$474.50
$/lb TP removed$2,300.52$3,428.44

Cost per pound = Present Worth / (pounds removed per year x service life). The present worth is discounted to today and the pounds are not. Annualized cost / pounds removed per year, another common form, gives a higher figure when the discount rate is above 0.