Summary Treatment Report: Net Improvement
Catchments and Associated BMP Types
| ID |
Catchment Name |
Catchment BMP |
Routing Destination |
| 1 |
catchment #1 |
Multiple BMP 1: Wet Detention 2: Stormwater Harvesting |
Routed to Outlet |
Volume of Runoff Summary
| Scenario |
Catchment Area (acres) |
Runoff Volume (ac-ft/yr) |
Runoff Volume (in/year) |
| Pre-Condition |
5.50 |
11.66 |
25.44 |
| System Post-Condition (with BMPs) |
5.00 |
8.54 |
20.49 |
| Post-Condition (no BMP) |
5.00 |
18.05 |
43.31 |
Runoff volumes are shown in acre-feet per year and converted to depth (inches/year) by dividing by area and multiplying by 12.
The catchment area is the same in both post rows: BMPs do not change the area, only how much runoff leaves it. Post-Condition (no BMP) is all the runoff the post-development catchments produce; System Post-Condition (with BMPs) is the runoff that leaves the system at the outlet. BMPs that keep water out of the surface discharge (retention, exfiltration, harvesting and the like) make the with-BMP volume smaller; BMPs that discharge to surface water (wet detention, surface discharge filtration) remove nutrient load but not volume, so the two volumes can be equal.
Summary of Removals
No Specified % Removals
Analysis Type: Net Improvement
There are no specified % removals defined for this analysis type.
Pre vs. Post Removals
| Pre/Post |
TN = 35.39%; |
TP = 35.39% |
| Provided |
TN = 74.55%; |
TP = 86.51% |
% Removal:
Is removal (pre<=post) for total nitrogen removal met?
Yes
Is removal (pre<=post) for total phosphorus removal met?
Yes
Pre/Post comparisons use analysis-type settings to derive required reductions. Values shown to two decimals unless noted.
Nitrogen & Phosphorus Loading
Surface water and groundwater loading summary
| Nitrogen (N) |
| Total N pre load | 17.97 kg/yr |
| Total N post load | 27.81 kg/yr |
| Target N load reduction | 35.39 % |
| Target N discharge load | 17.97 kg/yr |
| Percent N load reduction | 74.55 % |
| Provided N discharge load | 7.08 kg/yr (15.61 lb/yr) |
| Provided N load removed (surface) | 20.73 kg/yr (45.72 lb/yr) |
| Phosphorus (P) |
| Total P pre load | 2.487 kg/yr |
| Total P post load | 3.849 kg/yr |
| Target P load reduction | 35.39 % |
| Target P discharge load | 2.487 kg/yr |
| Percent P load reduction | 86.51 % |
| Provided P discharge load | 0.519 kg/yr (1.145 lb/yr) |
| Provided P load removed (surface) | 3.330 kg/yr (7.343 lb/yr) |
Values are project totals. Surface units = kg/yr; groundwater recharge in MG/yr and concentrations in mg/L. Values formatted to appropriate precision.