Unit Cost Summary Report

Project: Example #4 with harvesting pond   Date: 10/16/2026
Interest Rate: 3.3%   Project Duration: 30 years

Table 1 — BMP Lifecycle Cost Breakdown

CatchmentBMP Type Const. LowConst. High PV Repl. LowPV Repl. High PV O&M LowPV O&M High PV LowPV High Ann. LowAnn. High $/lb TN Low$/lb TN High $/lb TP Low$/lb TP High
catchment #1 Multiple BMP $175,000 $265,000 $34,240 $51,360 $99,420 $143,632 $308,660 $459,992 $16,364 $24,388 $225.04 $335.37 $1,401.19 $2,088.18
Project Totals $308,660 $459,992

Table 2 — Unit Cost Summary (FSAEF Format)

MetricTNTP
Annual Reduction (lbs/yr) 45.7 7.3
Lifecycle Reduction (lbs) 1,372 220
Unit Cost Low ($/lb) $225.04 $1,401.19
Unit Cost High ($/lb) $335.37 $2,088.18

Cost per pound = Present Worth / (pounds removed per year x service life). The present worth is discounted to today and the pounds are not. Annualized cost / pounds removed per year, another common form, gives a higher figure when the discount rate is above 0.