Project: Example #4 with harvesting pond
Date: 10/16/2026
Interest Rate: 3.3%
Project Duration: 30 years
| Catchment | BMP Type | Const. Low | Const. High | PV Repl. Low | PV Repl. High | PV O&M Low | PV O&M High | PV Low | PV High | Ann. Low | Ann. High | $/lb TN Low | $/lb TN High | $/lb TP Low | $/lb TP High |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| catchment #1 | Multiple BMP | $175,000 | $265,000 | $34,240 | $51,360 | $99,420 | $143,632 | $308,660 | $459,992 | $16,364 | $24,388 | $225.04 | $335.37 | $1,401.19 | $2,088.18 |
| Project Totals | $308,660 | $459,992 | |||||||||||||
| Metric | TN | TP |
|---|---|---|
| Annual Reduction (lbs/yr) | 45.7 | 7.3 |
| Lifecycle Reduction (lbs) | 1,372 | 220 |
| Unit Cost Low ($/lb) | $225.04 | $1,401.19 |
| Unit Cost High ($/lb) | $335.37 | $2,088.18 |
Cost per pound = Present Worth / (pounds removed per year x service life). The present worth is discounted to today and the pounds are not. Annualized cost / pounds removed per year, another common form, gives a higher figure when the discount rate is above 0.