Table 1 — Component Cost Detail

ComponentConst. LowConst. HighSvc LifeO&M% LowAnn O&M LowAnn O&M HighRepl. Cost Low (current $)Repl. Cost High (current $)# ReplRepl. at Time of Replacement LowRepl. at Time of Replacement HighPV Repl LowPV Repl HighPV O&M LowPV O&M High
Retention$100,000$150,000201.000%$1,000$9,000$100,000$150,0001$163,862$245,792$85,599$128,399$18,862$169,755
Outlet Structure, Fixed$10,000$15,000600.030%$3$60$10,000$15,0000$0$0$0$0$57$1,132

Replacement costs. A replacement cost is entered as the current cost (today's dollars, a present value); a blank replacement cost uses the construction cost. The cost at the time of each replacement (future value) is estimated with the inflation rate (2.5%): FV = Replacement Cost × (1 + inflation)k × Life, for replacements k = 1, 2, … that fall before the end of the 30-year analysis period (a component whose life is equal to or longer than the period is not replaced). Each future value is discounted to today with the discount rate (3.3%): PV = FV / (1 + discount)k × Life. PV of Replacement is the sum of those present values.

Table 2 — Routine Annual Costs

DescriptionQtyUnitAnnual LowAnnual HighPV LowPV High
Mowing / Vegetation Control / Litter Removal2each$3,700$3,700$69,788$69,788

Table 3 — Summary

Low EstimateHigh Estimate
Construction Cost$110,000$165,000
PV of Replacement$85,599$128,399
PV of O&M$88,707$240,675
Total PV (Present Worth)$284,306$534,074
Annualized PV (/yr)$15,073$28,315
$/lb TN removed$232.87$437.45
$/lb TP removed$1,260.48$2,367.83

Cost per pound = Present Worth / (pounds removed per year x service life). The present worth is discounted to today and the pounds are not. Annualized cost / pounds removed per year, another common form, gives a higher figure when the discount rate is above 0.