Routing 1 — Summary Report

Composite CN: pre-development pasture and woods
Made by BMPFast 2 on Tuesday, 20 October 2026 16:00

Summary Treatment Report: All sites non-exempted

Catchments and Associated BMP Types

IDCatchment NameCatchment BMPRouting Destination
1SiteNoneRouted to Outlet

Volume of Runoff Summary

ScenarioCatchment Area (acres)Runoff Volume (ac-ft/yr)Runoff Volume (in/year)
Pre-Condition20.006.103.66
System Post-Condition (with BMPs)20.0024.6614.80
Post-Condition (no BMP)20.0024.6614.80

Runoff volumes are shown in acre-feet per year and converted to depth (inches/year) by dividing by area and multiplying by 12.

The catchment area is the same in both post rows: BMPs do not change the area, only how much runoff leaves it. Post-Condition (no BMP) is all the runoff the post-development catchments produce; System Post-Condition (with BMPs) is the runoff that leaves the system at the outlet. BMPs that keep water out of the surface discharge (retention, exfiltration, harvesting and the like) make the with-BMP volume smaller; BMPs that discharge to surface water (wet detention, surface discharge filtration) remove nutrient load but not volume, so the two volumes can be equal.

Summary of Removals

Summary Loading:

Specified (for All sites non-exempted)TN = 55.00%;TP = 80.00%
ProvidedTN = 0.00%;TP = 0.00%

% Specified Removal:

Is specified removal for total nitrogen removal met? No

Is specified removal for total phosphorus removal met? No

Results are compared against the analysis type targets. Percentages are shown to two decimals.

Pre vs. Post Removals

Pre/PostTN = 57.68%;TP = 55.17%
ProvidedTN = 0.00%;TP = 0.00%

% Removal:

Is removal (pre<=post) for total nitrogen removal met? No

Is removal (pre<=post) for total phosphorus removal met? No

Pre/Post comparisons use analysis-type settings to derive required reductions. Values shown to two decimals unless noted.

Maximum Removals

MaximumTN = 57.68%;TP = 80.00%
ProvidedTN = 0.00%;TP = 0.00%

% Maximum Removal:

Is maximum removal for total nitrogen removal met? No

Is maximum removal for total phosphorus removal met? No

The maximum requirement is the greater of the Specified and Pre/Post removals. Percentages are shown to two decimals.

Nitrogen & Phosphorus Loading

Surface water and groundwater loading summary

Nitrogen (N)
Total N pre load22.77 kg/yr
Total N post load53.82 kg/yr
Percent N load reduction0.00 %
Provided N discharge load53.82 kg/yr (118.67 lb/yr)
Provided N load removed (surface)0.00 kg/yr (0.00 lb/yr)

Phosphorus (P)
Total P pre load4.457 kg/yr
Total P post load9.943 kg/yr
Percent P load reduction0.00 %
Provided P discharge load9.943 kg/yr (21.924 lb/yr)
Provided P load removed (surface)0.000 kg/yr (0.000 lb/yr)

Values are project totals. Surface units = kg/yr; groundwater recharge in MG/yr and concentrations in mg/L. Values formatted to appropriate precision.