Stormwater Harvesting — cost report
Example #4 with harvesting pond
Made by BMPFast 2 on Tuesday, 20 October 2026 16:00
Pounds removed counted in the treatment alone, as chosen on the Cost tab.
Table 1 — Component Cost Detail
| Component | Const. Low | Const. High | Svc Life | O&M% Low | Ann O&M Low | Ann O&M High | Repl. Cost Low (current $) | Repl. Cost High (current $) | # Repl | Repl. at Time of Replacement Low | Repl. at Time of Replacement High | PV Repl Low | PV Repl High | PV O&M Low | PV O&M High |
| Detention | ¤120,000 | ¤180,000 | 1000 | 0.005% | ¤6 | ¤450 | ¤120,000 | ¤180,000 | 0 | ¤0 | ¤0 | ¤0 | ¤0 | ¤113 | ¤8,488 |
| Pump Station, Intermittent | ¤40,000 | ¤60,000 | 20 | 0.500% | ¤200 | ¤1,800 | ¤40,000 | ¤60,000 | 1 | ¤65,545 | ¤98,317 | ¤34,240 | ¤51,360 | ¤3,772 | ¤33,951 |
| Piping, Force Main | ¤15,000 | ¤25,000 | 30 | 0.500% | ¤75 | ¤375 | ¤15,000 | ¤25,000 | 0 | ¤0 | ¤0 | ¤0 | ¤0 | ¤1,415 | ¤7,073 |
Replacement costs. A replacement cost is entered as the current cost (today's dollars, a present value); a blank replacement cost uses the construction cost. The cost at the time of each replacement (future value) is estimated with the inflation rate (2.5%): FV = Replacement Cost × (1 + inflation)k × Life, for replacements k = 1, 2, … that fall before the end of the 30-year analysis period (a component whose life is equal to or longer than the period is not replaced). Each future value is discounted to today with the discount rate (3.3%): PV = FV / (1 + discount)k × Life. PV of Replacement is the sum of those present values.
Table 2 — Routine Annual Costs
| Description | Qty | Unit | Annual Low | Annual High | PV Low | PV High |
| Mowing / Vegetation Control / Litter Removal | 4 | each | ¤7,400 | ¤7,400 | ¤139,577 | ¤139,577 |
| Stormwater Resale | 3.1 | MGY | (¤3,100) | (¤3,100) | (¤58,471) | (¤58,471) |
Section D — Electrical Energy
| Annual consumption | 6,000 kWh/yr |
| Rate | 0.115 $/kWh |
| Annual electrical cost | ¤690 |
| PV of electrical cost | ¤13,015 |
Table 3 — Summary
| Low Estimate | High Estimate |
| Construction Cost | ¤175,000 | ¤265,000 |
| PV of Replacement | ¤34,240 | ¤51,360 |
| PV of O&M | ¤99,420 | ¤143,632 |
| Total PV (Present Worth) | ¤308,660 | ¤459,992 |
| Annualized PV (/yr) | ¤16,364 | ¤24,388 |
| $/lb TN removed | ¤318.39 | ¤474.50 |
| $/lb TP removed | ¤2,300.52 | ¤3,428.44 |
Cost per pound = Present Worth / (pounds removed per year x service life). The present worth is discounted to today and the pounds are not. Annualized cost / pounds removed per year, another common form, gives a higher figure when the discount rate is above 0.