Routing 1, at a discount rate of 3.30 % over 30 years.
Project: Example #4 with harvesting pond Date: 10/20/2026
Interest Rate: 3.3% Project Duration: 30 years
| Catchment | BMP Type | Const. Low | Const. High | PV Repl. Low | PV Repl. High | PV O&M Low | PV O&M High | PV Low | PV High | Ann. Low | Ann. High | $/lb TN Low | $/lb TN High | $/lb TP Low | $/lb TP High |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| catchment #1 | Multiple BMP | ¤175,000 | ¤265,000 | ¤34,240 | ¤51,360 | ¤99,420 | ¤143,632 | ¤308,660 | ¤459,992 | ¤16,364 | ¤24,388 | ¤212.88 | ¤317.25 | ¤1,335.46 | ¤1,990.22 |
| Project Totals | ¤308,660 | ¤459,992 |
| Metric | TN | TP |
|---|---|---|
| Annual Reduction (lbs/yr) | 48.3 | 7.7 |
| Lifecycle Reduction (lbs) | 1,450 | 231 |
| Unit Cost Low ($/lb) | ¤212.88 | ¤1,335.46 |
| Unit Cost High ($/lb) | ¤317.25 | ¤1,990.22 |
Cost per pound = Present Worth / (pounds removed per year x service life). The present worth is discounted to today and the pounds are not. Annualized cost / pounds removed per year, another common form, gives a higher figure when the discount rate is above 0.