Cost analysis 1 — Full cost report

Example Problem # 3
Made by BMPFast 2 on Tuesday, 20 October 2026 16:00

Routing 1, at a discount rate of 3.30 % over 30 years.

Full Cost Report — Per BMP

Project: Example Problem # 3 Date: 10/20/2026

Discount Rate: 3.3% Project Duration: 30 years

Section 1 — Cost Components

catchment 1 — Retention

Component NameConst. Low ($)Const. High ($)Service Life (yr)O&M % LowO&M % HighAnnual O&M Low ($)Annual O&M High ($)Repl. Low (current $)Repl. High (current $)# ReplacementsRepl. at Time of Replacement Low ($)Repl. at Time of Replacement High ($)PV Repl. Low ($)PV Repl. High ($)PV O&M Low ($)PV O&M High ($)
Retention¤100,000¤150,000201.00006.0000¤1,000¤9,000¤100,000¤150,0001¤163,862¤245,792¤85,599¤128,399¤18,862¤169,755
Outlet Structure, Fixed¤10,000¤15,000600.03000.4000¤3¤60¤10,000¤15,0000¤0¤0¤0¤0¤57¤1,132
TOTALS¤110,000¤165,000¤1,003¤9,060¤85,599¤128,399¤18,918¤170,887

Replacement costs. A replacement cost is entered as the current cost (today's dollars, a present value); a blank replacement cost uses the construction cost. The cost at the time of each replacement (future value) is estimated with the inflation rate (2.5%): FV = Replacement Cost × (1 + inflation)k × Life, for replacements k = 1, 2, … that fall before the end of the 30-year analysis period (a component whose life is equal to or longer than the period is not replaced). Each future value is discounted to today with the discount rate (3.3%): PV = FV / (1 + discount)k × Life. PV of Replacement is the sum of those present values.

Section 2 — Routine Maintenance Costs

catchment 1 — Retention

DescriptionUnitQuantity$/Unit Low$/Unit HighAnnual Low ($)Annual High ($)PV Low ($)PV High ($)
Mowing / Vegetation Control / Litter Removaleach2.00¤1,850.00¤1,850.00¤3,700¤3,700¤69,788¤69,788
TOTALS¤3,700¤3,700¤69,788¤69,788