Routing 1 — Summary Report

Ex # 5 ret to det one catch
Made by BMPFast 2 on Tuesday, 20 October 2026 16:00

Summary Treatment Report: Specified Removal Efficiency

Catchments and Associated BMP Types

IDCatchment NameCatchment BMPRouting Destination
1Highway Section 206Multiple BMP 1: Retention 2: Wet DetentionRouted to Outlet

Volume of Runoff Summary

ScenarioCatchment Area (acres)Runoff Volume (ac-ft/yr)Runoff Volume (in/year)
Pre-Condition6.004.799.58
System Post-Condition (with BMPs)5.005.2612.63
Post-Condition (no BMP)5.0013.9033.37

Runoff volumes are shown in acre-feet per year and converted to depth (inches/year) by dividing by area and multiplying by 12.

The catchment area is the same in both post rows: BMPs do not change the area, only how much runoff leaves it. Post-Condition (no BMP) is all the runoff the post-development catchments produce; System Post-Condition (with BMPs) is the runoff that leaves the system at the outlet. BMPs that keep water out of the surface discharge (retention, exfiltration, harvesting and the like) make the with-BMP volume smaller; BMPs that discharge to surface water (wet detention, surface discharge filtration) remove nutrient load but not volume, so the two volumes can be equal.

Summary of Removals

Summary Loading:

Specified (for Specified Removal Efficiency)TN = 70.00%;TP = 80.00%
ProvidedTN = 79.87%;TP = 92.37%

% Specified Removal:

Is specified removal for total nitrogen removal met? Yes

Is specified removal for total phosphorus removal met? Yes

Results are compared against the analysis type targets. Percentages are shown to two decimals.

No Pre/Post Analysis

Analysis Type: Specified Removal Efficiency

There are no pre/post targets for this analysis type.

Nitrogen & Phosphorus Loading

Surface water and groundwater loading summary

Nitrogen (N)
Total N pre load7.16 kg/yr
Total N post load21.43 kg/yr
Target N load reduction70.00 %
Target N discharge load6.43 kg/yr
Percent N load reduction79.87 %
Provided N discharge load4.31 kg/yr (9.51 lb/yr)
Provided N load removed (surface)17.11 kg/yr (37.74 lb/yr)

Phosphorus (P)
Total P pre load0.124 kg/yr
Total P post load2.966 kg/yr
Target P load reduction80.00 %
Target P discharge load0.593 kg/yr
Percent P load reduction92.37 %
Provided P discharge load0.226 kg/yr (0.499 lb/yr)
Provided P load removed (surface)2.739 kg/yr (6.041 lb/yr)

Values are project totals. Surface units = kg/yr; groundwater recharge in MG/yr and concentrations in mg/L. Values formatted to appropriate precision.