Calculated with v1's engine, by Strand routing (v1's routing; use this for permits), so an opened v1 project gives the numbers v1 gives. This is the summary; v1's reports for this routing (Summary, Complete, Flow Balance, Full Routing Diagram, compliance, catchments and their treatments) are in the Report list above.

Nitrogen

Total Outlet Nitrogen Loading1.35 kg/yr
Total Catchment Nitrogen Loading2.53 kg/yr
Provided Nitrogen Treatment Efficiency46.50 %

Phosphorus

Total Outlet Phosphorus Loading0.28 kg/yr
Total Catchment Phosphorus Loading0.52 kg/yr
Provided Phosphorus Treatment Efficiency46.50 %

Runoff and area

Pre-development runoff volume0.24 ac-ft/yr
Post-development runoff volume leaving the site1.18 ac-ft/yr
Pre-Condition Catchment Area1.00 ac
Post Condition Catchment Area1.00 ac

Requirement

Type of analysisBMP Analysis

This type of analysis sets no removal to meet, so there is no pass or fail here.

How each catchment is routed

CatchmentDrains toTreatment usedLeft out
ParkingOutletVegetated Filter Strip