Routing 1

Retention efficiency lookup: Zone 4, between tables — Catchment Routing results
Made by BMPFast 2 on Tuesday, 20 October 2026 16:00

Calculated with v1's engine, by Strand routing (v1's routing; use this for permits), so an opened v1 project gives the numbers v1 gives. This is the summary; v1's reports for this routing (Summary, Complete, Flow Balance, Full Routing Diagram, compliance, catchments and their treatments) are in the Report list above.

Nitrogen

Total Outlet Nitrogen Loading13.54 kg/yr
Total Catchment Nitrogen Loading39.43 kg/yr
Provided Nitrogen Treatment Efficiency65.65 %

Phosphorus

Total Outlet Phosphorus Loading1.95 kg/yr
Total Catchment Phosphorus Loading5.67 kg/yr
Provided Phosphorus Treatment Efficiency65.65 %

Runoff and area

Pre-development runoff volume1.54 ac-ft/yr
Post-development runoff volume leaving the site4.58 ac-ft/yr
Pre-Condition Catchment Area5.00 ac
Post Condition Catchment Area5.00 ac

Requirement

Type of analysisBMP Analysis

This type of analysis sets no removal to meet, so there is no pass or fail here.

How each catchment is routed

CatchmentDrains toTreatment usedLeft out
Commercial siteOutletRetention