Routing 1 — Complete Report

no BMP upstream detention
Made by BMPFast 2 on Tuesday, 20 October 2026 16:00

Summary Treatment Report: Specified Removal Efficiency

Catchments and Associated BMP Types

IDCatchment NameCatchment BMPRouting Destination
1downstreamWet DetentionRouted to Outlet
2upstreamNo TreatmentRouted to Catchment 1

Catchment #1 - downstream

Catchment Characteristics

Catchment Namedownstream
Rainfall ZoneFlorida Zone 2
Annual Mean Rainfall50.00 in

Pre-Condition Watershed Characteristics

Pre-Condition LanduseUser Defined Values
Pre Condition Area1.00 acres
Pre Annual Runoff Coefficient, ROC (0-1)0.24
Pre Non DCIA Curve Number70.00
Pre DCIA Percent (0-100)24.33
Pre Nitrogen EMC0.81 mg/l
Pre Phosphorus EMC0.81 mg/l
Pre Runoff Volume1.00 ac-ft/yr
Pre Nitrogen Loading1.00 kg/yr
Pre Phosphorus Loading1.00 kg/yr

Post-Condition Watershed Characteristics

Post-Condition LanduseUser Defined Values
Post Condition Area1.00 acres
Post Annual Runoff Coefficient, ROC (0-1)0.24
Post Non DCIA Curve Number70.00
Post DCIA Percent (0-100)24.33
Post Nitrogen EMC0.81 mg/l
Post Phosphorus EMC0.81 mg/l
Post Runoff Volume1.00 ac-ft/yr
Post Nitrogen Loading1.00 kg/yr
Post Phosphorus Loading1.00 kg/yr

Wet Detention Input Variables

Permanent Pool Volume0.10 ac-ft
Permanent Pool Volume for 31 days residence8.49 ac-ft
Average Residence Time0.36 days
Has Littoral ZoneYes
Wetland Efficiency Credit0.00 %

Littoral zone: the pond has one, so a credit of 10.00 percentage points is added to the N and P removal from the wet pond equations (Appendix O, Table 1: "Maximum 10% removal with a minimum littoral zone area"; the equations are taken as a pond without one).

Catchment #2 - upstream

Catchment Characteristics

Catchment Nameupstream
Rainfall ZoneFlorida Zone 2
Annual Mean Rainfall50.00 in

Pre-Condition Watershed Characteristics

Pre-Condition LanduseUser Defined Values
Pre Condition Area99.00 acres
Pre Annual Runoff Coefficient, ROC (0-1)0.24
Pre Non DCIA Curve Number70.00
Pre DCIA Percent (0-100)24.33
Pre Nitrogen EMC0.81 mg/l
Pre Phosphorus EMC0.81 mg/l
Pre Runoff Volume99.02 ac-ft/yr
Pre Nitrogen Loading99.01 kg/yr
Pre Phosphorus Loading99.01 kg/yr

Post-Condition Watershed Characteristics

Post-Condition LanduseUser Defined Values
Post Condition Area99.00 acres
Post Annual Runoff Coefficient, ROC (0-1)0.24
Post Non DCIA Curve Number70.00
Post DCIA Percent (0-100)24.33
Post Nitrogen EMC0.81 mg/l
Post Phosphorus EMC0.81 mg/l
Post Runoff Volume99.02 ac-ft/yr
Post Nitrogen Loading99.01 kg/yr
Post Phosphorus Loading99.01 kg/yr

Volume of Runoff Summary

ScenarioCatchment Area (acres)Runoff Volume (ac-ft/yr)Runoff Volume (in/year)
Pre-Condition100.00100.0212.00
System Post-Condition (with BMPs)100.00100.0212.00
Post-Condition (no BMP)100.00100.0212.00

Runoff volumes are shown in acre-feet per year and converted to depth (inches/year) by dividing by area and multiplying by 12.

The catchment area is the same in both post rows: BMPs do not change the area, only how much runoff leaves it. Post-Condition (no BMP) is all the runoff the post-development catchments produce; System Post-Condition (with BMPs) is the runoff that leaves the system at the outlet. BMPs that keep water out of the surface discharge (retention, exfiltration, harvesting and the like) make the with-BMP volume smaller; BMPs that discharge to surface water (wet detention, surface discharge filtration) remove nutrient load but not volume, so the two volumes can be equal.

Summary of Removals

Summary Loading:

Specified (for Specified Removal Efficiency)TN = 75.00%;TP = 75.00%
ProvidedTN = 13.36%;TP = 43.92%

% Specified Removal:

Is specified removal for total nitrogen removal met? No

Is specified removal for total phosphorus removal met? No

Results are compared against the analysis type targets. Percentages are shown to two decimals.

No Pre/Post Analysis

Analysis Type: Specified Removal Efficiency

There are no pre/post targets for this analysis type.

Nitrogen & Phosphorus Loading

Surface water and groundwater loading summary

Nitrogen (N)
Total N pre load100.01 kg/yr
Total N post load100.01 kg/yr
Target N load reduction75.00 %
Target N discharge load25.00 kg/yr
Percent N load reduction13.36 %
Provided N discharge load86.65 kg/yr (191.06 lb/yr)
Provided N load removed (surface)13.37 kg/yr (29.47 lb/yr)

Phosphorus (P)
Total P pre load100.014 kg/yr
Total P post load100.014 kg/yr
Target P load reduction75.00 %
Target P discharge load25.003 kg/yr
Percent P load reduction43.92 %
Provided P discharge load56.084 kg/yr (123.666 lb/yr)
Provided P load removed (surface)43.929 kg/yr (96.864 lb/yr)

Values are project totals. Surface units = kg/yr; groundwater recharge in MG/yr and concentrations in mg/L. Values formatted to appropriate precision.