Greenroof on an office building

Half an acre of greenroof, no cistern, Orlando; BMP Analysis.

1The problem

A half-acre office roof in Orlando is built as a greenroof. Its filtrate is not stored (no cistern).

InputValueSource
Project (General Site Information)
Meteorological zoneFlorida Zone 2Zone map (help page 815)
Mean annual rainfall50 inMean annual rainfall map (help page 815)
Performance standard (analysis type)BMP AnalysisSite (illustrative)
Catchment 1: Office roof (Watershed Characteristics)
Land use, pre / postUndeveloped - Mesic Flatwoods / Conventional RoofsSite (illustrative)
Area, pre / post0.5 / 0.5 acSite (illustrative)
Non-DCIA curve number, pre / post70 / 98Site (illustrative)
DCIA, pre / post0 / 100 %Site (illustrative)
EMC TN, pre / post1.087 / 1.050 mg/LBMPFast land use table (AH Vol I Table 9.2)
EMC TP, pre / post0.043 / 0.120 mg/LBMPFast land use table (AH Vol I Table 9.2)
Greenroof (worksheet)
Rainfall stationOrlando #6628Design (illustrative)
Greenroof area21780 sfDesign (illustrative)
Cistern storage over greenroof area0 inDesign (illustrative)
Irrigation demand0 in/yrDesign (illustrative)
Rainfall excess (filtrate underdrain flow)0 in/yrDesign (illustrative)

Find: the TN and TP removal of the BMP, the loads leaving the site, and whether the performance standard is met.

2Steps in BMPFast 2

  1. Start BMPFast 2 and choose File ▸ New project. The tree on the left opens on the project (General Site Information). On its Entry tab enter: Project name Greenroof: office roof, no cistern; Meteorological zone Florida Zone 2; Mean annual rainfall 50.00 in; Type of analysis BMP Analysis. (To follow along with the finished project instead, choose File ▸ Open and open greenroof-no-cistern.bmpf from Files below.)

    General Site Information: the project’s Entry tab.
    General Site Information: the project’s Entry tab.
  2. Press Add Catchment (left). Select the new catchment in the tree; on its Entry tab type the name Office roof and enter: Land use (pre) Undeveloped - Mesic Flatwoods; Land use (post) Conventional Roofs; Area (pre) 0.50 ac; Area (post) 0.50 ac; Non-DCIA curve number (pre) 70.00; Non-DCIA curve number (post) 98.00; DCIA (post) 100.00 %. Leave the other boxes as they are (0 or blank). BMPFast 2 calculates as you type; scroll down to Calculated for the results after development: Annual runoff coefficient (ROC) (post) 0.809; Runoff volume (post) 1.685 ac-ft/yr; Nitrogen load (post) 2.182 kg/yr; Phosphorus load (post) 0.249 kg/yr.

    The catchment Office roof: its Entry tab.
    The catchment Office roof: its Entry tab.
  3. With Office roof selected, press Add Treatment and choose Greenroof. On its Entry tab type the Treatment name Greenroof (BMPFast 2 starts it as “Greenroof 1”) and enter: Removal method Rainfall station curves; Rainfall station Orlando #6628; Greenroof area 21,780.00 ft². The results are calculated as you type: Hydraulic capture 43.00 %; Nitrogen removal provided 43.00 %; Phosphorus removal provided 43.00 %.

    The treatment Greenroof: its Entry tab.
    The treatment Greenroof: its Entry tab.
  4. Open the treatment’s Report tab: its inputs and removal, as a report to print or save.

    The treatment Greenroof: its Report tab.
    The treatment Greenroof: its Report tab.
  5. Press Add Routing (left). BMPFast 2 adds Routing 1 under Catchment Routings, with every catchment draining to the outlet and no treatment; a project can have several routings, compared side by side. On its Entry tab (How the routing is calculated Strand routing (v1's routing; use this for permits)) set each catchment as in this table:

    CatchmentDrains toTreatment used
    Office roofOutletGreenroof

    A catchment is treated only by the treatment its routing uses.

    The routing’s Entry tab: where each catchment drains and the treatment it uses.
    The routing’s Entry tab: where each catchment drains and the treatment it uses.
  6. Open the routing’s Report tab. Results shows the loads leaving the site, the removal provided and required, and whether the performance standard is met; the list at the top of the tab has v1’s reports for the same routing (Summary, Complete, Flow Balance, AH Vol I Sec 9 compliance). Save the project with File ▸ Save; compare it with the .bmpf under Files.

    The routing’s Report tab: Results.
    The routing’s Report tab: Results.

3Results

ResultValue
Catchment 1: computed by BMPFast
Annual runoff coefficient (ROC), pre / post0.057 / 0.809
Runoff, pre / post0.119 / 1.685 ac-ft/yr
TN load, pre / post0.159 / 2.182 kg/yr
TP load, pre / post0.006 / 0.249 kg/yr
Greenroof: computed by BMPFast
Hydraulic capture efficiency43.00 %
Provided TN / TP removal43.00 % / 43.00 %
TN load in → out2.182 → 1.244 kg/yr
TP load in → out0.249 → 0.142 kg/yr
Site (all catchments, at the outlet)
TN load: catchments → outlet2.182 → 1.244 kg/yr
TP load: catchments → outlet0.249 → 0.142 kg/yr
Provided removal TN / TP43.0 % / 43.0 %

The BMP report

Open this report on its own page.

The Summary Report

Open this report on its own page.

BMPFast 2 and BMPFast (v1)

ResultBMPFast 2BMPFast (v1), its page
Nitrogen leaving the site1.244 kg/yr1.244 kg/yrsame
Phosphorus leaving the site0.142 kg/yr0.142 kg/yrsame
Site removal, nitrogen43.000 %43.000 %same
Site removal, phosphorus43.000 %43.000 %same
Office roof: Greenroof removal, nitrogen43.000 %43.000 %same
Office roof: Greenroof removal, phosphorus43.000 %43.000 %same

Every number BMPFast 2 gives for this problem is the same as BMPFast (v1)’s, to three decimals.

4Check

Runoff and loads (Equations 9-1 and 9-2 of AH Vol I).

1.233 kg is 1 mg/L in 1 ac-ft.

Capture. With no cistern the greenroof alone retains 43.00 % of the annual runoff (the program’s greenroof value for Orlando #6628). The water that stays on the roof keeps its nitrogen and phosphorus, so the TN and TP removal equal the capture (Harvesting and Greenroof Methodology).

Load out.

The program’s Equations page

Open this report on its own page.

5Files

  • greenroof-no-cistern.bmpf: the project, saved by BMPFast 2. Save it (your browser puts it in Downloads), then in BMPFast 2 choose File ▸ Open and open it. Opened again and calculated, it gives the numbers on this page.
  • greenroof-no-cistern.bmpt: the same project as BMPFast (v1) saved it. BMPFast 2 opens it too (File ▸ Open); saving it then makes a .bmpf and leaves the .bmpt as it was.
  • Routing 1 (BMPFast 2’s report, as Open in browser on its Report tab gives it)
  • Routing 1 — Summary Report (BMPFast 2’s report, as Open in browser on its Report tab gives it)
  • Greenroof (BMPFast 2’s report, as Open in browser on its Report tab gives it)
  • Greenroof — calculations (BMPFast 2’s report, as Open in browser on its Report tab gives it)

6Help and methodology

Calculated with BMPFast 2 version 2.0.0 (2026-10-20), which opens the problem’s v1 project as it is. Screen captures are of BMPFast 2’s own window and are for demonstration only.