Retention rain garden in a parking island

A rain garden that infiltrates, with B&G ECT media; BMP Analysis, Zone 2.

1The problem

A half-acre parking lot drains to a rain garden in a parking island that infiltrates (retention). It holds 600 cf above the media and 1,200 cf of native soil with a void fraction of 0.3.

InputValueSource
Project (General Site Information)
Meteorological zoneFlorida Zone 2Zone map (help page 815)
Mean annual rainfall50 inMean annual rainfall map (help page 815)
Performance standard (analysis type)BMP AnalysisSite (illustrative)
Catchment 1: Parking lot (Watershed Characteristics)
Land use, pre / postUndeveloped - Mesic Flatwoods / Low-Intensity CommercialSite (illustrative)
Area, pre / post0.5 / 0.5 acSite (illustrative)
Non-DCIA curve number, pre / post70 / 80Site (illustrative)
DCIA, pre / post0 / 80 %Site (illustrative)
EMC TN, pre / post1.087 / 0.930 mg/LBMPFast land use table (AH Vol I Table 9.2)
EMC TP, pre / post0.043 / 0.190 mg/LBMPFast land use table (AH Vol I Table 9.2)
Media mixB&G ECT Mixes (TN 45 %, TP 45 %)BMPFast media table (help page 817)
Rain Garden Analysis (worksheet)
System TypeRetentionDesign (illustrative)
Sustainable Void Fraction0.3Design (illustrative)
Native Soil Volume1200 cubic feetDesign (illustrative)
Water Storage above Media600 cubic feetDesign (illustrative)
Credit for Native Soil and Cover Crop0 %Design (illustrative)

Find: the TN and TP removal of the BMP, the loads leaving the site, and whether the performance standard is met.

2Steps in BMPFast 2

  1. Start BMPFast 2 and choose File ▸ New project. The tree on the left opens on the project (General Site Information). On its Entry tab enter: Project name Rain garden: retention, parking island; Meteorological zone Florida Zone 2; Mean annual rainfall 50.00 in; Type of analysis BMP Analysis; Conduct groundwater discharge analysis Yes. (To follow along with the finished project instead, choose File ▸ Open and open rain-garden-retention.bmpf from Files below.)

    General Site Information: the project’s Entry tab.
    General Site Information: the project’s Entry tab.
  2. Press Add Catchment (left). Select the new catchment in the tree; on its Entry tab type the name Parking lot and enter: Land use (pre) Undeveloped - Mesic Flatwoods; Land use (post) Low-Intensity Commercial; Area (pre) 0.50 ac; Area (post) 0.50 ac; Non-DCIA curve number (pre) 70.00; Non-DCIA curve number (post) 80.00; DCIA (post) 80.00 %. Leave the other boxes as they are (0 or blank). BMPFast 2 calculates as you type; scroll down to Calculated for the results after development: Annual runoff coefficient (ROC) (post) 0.670; Runoff volume (post) 1.396 ac-ft/yr; Nitrogen load (post) 1.601 kg/yr; Phosphorus load (post) 0.327 kg/yr.

    The catchment Parking lot: its Entry tab.
    The catchment Parking lot: its Entry tab.
  3. With Parking lot selected, press Add Treatment and choose Rain Garden. On its Entry tab type the Treatment name Rain Garden (BMPFast 2 starts it as “Rain Garden 1”) and enter: System type Retention; Sustainable void fraction 0.30; Native soil volume 1,200 ft³; Water storage above the media 600.00 ft³; Media mix B&G ECT Mixes; Is the media design residence time more than 2 hours? Yes; Media nitrogen reduction 45.00 %; Media phosphorus reduction 45.00 %. The results are calculated as you type: Provided retention volume 0.022 ac-ft; Provided media treatment depth 0.53 in; Minimum media area to drain in 48 hours 2 ft²; Nitrogen removal provided 52.27 %; Phosphorus removal provided 52.27 %.

    The treatment Rain Garden: its Entry tab.
    The treatment Rain Garden: its Entry tab.
  4. Open the treatment’s Report tab: its inputs and removal, as a report to print or save.

    The treatment Rain Garden: its Report tab.
    The treatment Rain Garden: its Report tab.
  5. Press Add Routing (left). BMPFast 2 adds Routing 1 under Catchment Routings, with every catchment draining to the outlet and no treatment; a project can have several routings, compared side by side. On its Entry tab (How the routing is calculated Strand routing (v1's routing; use this for permits)) set each catchment as in this table:

    CatchmentDrains toTreatment used
    Parking lotOutletRain Garden

    A catchment is treated only by the treatment its routing uses.

    The routing’s Entry tab: where each catchment drains and the treatment it uses.
    The routing’s Entry tab: where each catchment drains and the treatment it uses.
  6. Open the routing’s Report tab. Results shows the loads leaving the site, the removal provided and required, and whether the performance standard is met; the list at the top of the tab has v1’s reports for the same routing (Summary, Complete, Flow Balance, AH Vol I Sec 9 compliance). Save the project with File ▸ Save; compare it with the .bmpf under Files.

    The routing’s Report tab: Results.
    The routing’s Report tab: Results.

3Results

ResultValue
Catchment 1: computed by BMPFast
Annual runoff coefficient (ROC), pre / post0.057 / 0.670
Runoff, pre / post0.119 / 1.396 ac-ft/yr
TN load, pre / post0.159 / 1.601 kg/yr
TP load, pre / post0.006 / 0.327 kg/yr
Rain Garden: computed by BMPFast
Treatment depth0.529 in
Hydraulic capture efficiency52.27 %
Provided TN / TP removal52.27 % / 52.27 %
TN load in → out1.601 → 0.764 kg/yr
TP load in → out0.327 → 0.156 kg/yr
Site (all catchments, at the outlet)
TN load: catchments → outlet1.601 → 0.764 kg/yr
TP load: catchments → outlet0.327 → 0.156 kg/yr
Provided removal TN / TP52.3 % / 52.3 %

The BMP report

Open this report on its own page.

The Summary Report

Open this report on its own page.

BMPFast 2 and BMPFast (v1)

ResultBMPFast 2BMPFast (v1), its page
Nitrogen leaving the site0.764 kg/yr0.764 kg/yrsame
Phosphorus leaving the site0.156 kg/yr0.156 kg/yrsame
Site removal, nitrogen52.274 %52.274 %same
Site removal, phosphorus52.274 %52.274 %same
Parking lot: Rain Garden removal, nitrogen52.274 %52.274 %same
Parking lot: Rain Garden removal, phosphorus52.274 %52.274 %same

Every number BMPFast 2 gives for this problem is the same as BMPFast (v1)’s, to three decimals.

4Check

Runoff and loads (Equations 9-1 and 9-2 of AH Vol I).

1.233 kg is 1 mg/L in 1 ac-ft.

Storage.

Treatment depth.

Capture. The retention efficiency tables for Florida Zone 2 at a treatment depth of 0.529 in, non-DCIA CN 80.00 and DCIA 80.0 % give a hydraulic capture of 52.27 % (AH Vol I Appendix O; read the same tables with Calculators ▸ Retention Efficiency Tables, help page 4325). A retention rain garden keeps what it captures: the removal equals the capture. The media then treat the water going to the groundwater (post-media groundwater removal 32.15 %).

Load out.

The program’s Equations page

Open this report on its own page.

5Files

  • rain-garden-retention.bmpf: the project, saved by BMPFast 2. Save it (your browser puts it in Downloads), then in BMPFast 2 choose File ▸ Open and open it. Opened again and calculated, it gives the numbers on this page.
  • rain-garden-retention.bmpt: the same project as BMPFast (v1) saved it. BMPFast 2 opens it too (File ▸ Open); saving it then makes a .bmpf and leaves the .bmpt as it was.
  • Routing 1 (BMPFast 2’s report, as Open in browser on its Report tab gives it)
  • Routing 1 — Summary Report (BMPFast 2’s report, as Open in browser on its Report tab gives it)
  • Rain Garden (BMPFast 2’s report, as Open in browser on its Report tab gives it)
  • Rain Garden — calculations (BMPFast 2’s report, as Open in browser on its Report tab gives it)

6Help and methodology

Calculated with BMPFast 2 version 2.0.0 (2026-10-20), which opens the problem’s v1 project as it is. Screen captures are of BMPFast 2’s own window and are for demonstration only.