Wet detention for a commercial site discharging to an impaired water
A 6.0 ac-ft pool, no littoral zone; Impaired Water, Zone 3.
Help: Wet Detention (help page 211) · Download the .bmpf · Link to Solution in BMPFast Version 1
1The problem
A 5-acre high-intensity commercial site on former flatwoods discharges to an impaired water. Its wet pond has a 6.0 ac-ft permanent pool and no littoral zone.
| Input | Value | Source |
|---|---|---|
| Project (General Site Information) | ||
| Meteorological zone | Florida Zone 3 | Zone map (help page 815) |
| Mean annual rainfall | 54 in | Mean annual rainfall map (help page 815) |
| Performance standard (analysis type) | Impaired Water | Site (illustrative) |
| Catchment 1: Commercial site (Watershed Characteristics) | ||
| Land use, pre / post | Undeveloped - Mesic Flatwoods / High-Intensity Commercial | Site (illustrative) |
| Area, pre / post | 5 / 5 ac | Site (illustrative) |
| Non-DCIA curve number, pre / post | 70 / 80 | Site (illustrative) |
| DCIA, pre / post | 0 / 70 % | Site (illustrative) |
| EMC TN, pre / post | 1.087 / 2.400 mg/L | BMPFast land use table (AH Vol I Table 9.2) |
| EMC TP, pre / post | 0.043 / 0.345 mg/L | BMPFast land use table (AH Vol I Table 9.2) |
| Wet Detention (worksheet) | ||
| Permanent Pool Volume | 6.0 ac-ft | Design (illustrative) |
| There is a littoral zone | unticked | Design (illustrative) |
| Floating Wetland or other MAPs Credit | 0 % | Design (illustrative) |
Find: the TN and TP removal of the BMP, the loads leaving the site, and whether the performance standard is met.
2Steps in BMPFast 2
Start BMPFast 2 and choose File ▸ New project. The tree on the left opens on the project (General Site Information). On its Entry tab enter: Project name Wet detention: commercial site, impaired water; Meteorological zone Florida Zone 3; Mean annual rainfall 54.00 in; Type of analysis Impaired Water. (To follow along with the finished project instead, choose File ▸ Open and open
wet-detention-impaired.bmpffrom Files below.)
General Site Information: the project’s Entry tab. Press Add Catchment (left). Select the new catchment in the tree; on its Entry tab type the name Commercial site and enter: Land use (pre) Undeveloped - Mesic Flatwoods; Land use (post) High-Intensity Commercial; Area (pre) 5.00 ac; Area (post) 5.00 ac; Non-DCIA curve number (pre) 70.00; Non-DCIA curve number (post) 80.00; DCIA (post) 70.00 %. Leave the other boxes as they are (0 or blank). BMPFast 2 calculates as you type; scroll down to Calculated for the results after development: Annual runoff coefficient (ROC) (post) 0.596; Runoff volume (post) 13.410 ac-ft/yr; Nitrogen load (post) 39.683 kg/yr; Phosphorus load (post) 5.704 kg/yr.

The catchment Commercial site: its Entry tab. With Commercial site selected, press Add Treatment and choose Wet Detention. On its Entry tab type the Treatment name Wet Detention (BMPFast 2 starts it as “Wet Detention 1”) and enter: Permanent pool volume 6.000 ac-ft; How the littoral zone counts Littoral zone credit (BMPFast 2). The results are calculated as you type: Average residence time 163.31 days; Permanent pool volume for 31 days residence 1.14 ac-ft; Nitrogen removal provided 42.61 %; Phosphorus removal provided 78.13 %.

The treatment Wet Detention: its Entry tab. Open the treatment’s Report tab: its inputs and removal, as a report to print or save.

The treatment Wet Detention: its Report tab. Press Add Routing (left). BMPFast 2 adds Routing 1 under Catchment Routings, with every catchment draining to the outlet and no treatment; a project can have several routings, compared side by side. On its Entry tab (How the routing is calculated Strand routing (v1's routing; use this for permits)) set each catchment as in this table:
Catchment Drains to Treatment used Commercial site Outlet Wet Detention A catchment is treated only by the treatment its routing uses.

The routing’s Entry tab: where each catchment drains and the treatment it uses. Open the routing’s Report tab. Results shows the loads leaving the site, the removal provided and required, and whether the performance standard is met; the list at the top of the tab has v1’s reports for the same routing (Summary, Complete, Flow Balance, AH Vol I Sec 9 compliance). Save the project with File ▸ Save; compare it with the .bmpf under Files.

The routing’s Report tab: Results.
3Results
| Result | Value |
|---|---|
| Catchment 1: computed by BMPFast | |
| Annual runoff coefficient (ROC), pre / post | 0.078 / 0.596 |
| Runoff, pre / post | 1.755 / 13.410 ac-ft/yr |
| TN load, pre / post | 2.352 / 39.683 kg/yr |
| TP load, pre / post | 0.093 / 5.704 kg/yr |
| Wet Detention: computed by BMPFast | |
| Annual residence time | 163.3 days |
| Hydraulic capture efficiency | 70.00 % |
| Provided TN / TP removal | 42.61 % / 78.13 % |
| TN load in → out | 39.683 → 22.775 kg/yr |
| TP load in → out | 5.704 → 1.248 kg/yr |
| Site (all catchments, at the outlet) | |
| TN load: catchments → outlet | 39.683 → 22.775 kg/yr |
| TP load: catchments → outlet | 5.704 → 1.248 kg/yr |
| Provided removal TN / TP | 42.6 % / 78.1 % |
| Required removal TN / TP (Maximum % Removal) | 94.1 % (not met) / 98.4 % (not met) |
The BMP report
Open this report on its own page.
The Summary Report
Open this report on its own page.
BMPFast 2 and BMPFast (v1)
| Result | BMPFast 2 | BMPFast (v1), its page | |
|---|---|---|---|
| Nitrogen leaving the site | 22.775 kg/yr | 24.466 kg/yr | differs |
| Phosphorus leaving the site | 1.248 kg/yr | 1.693 kg/yr | differs |
| Site removal, nitrogen | 42.607 % | 38.347 % | differs |
| Site removal, phosphorus | 78.130 % | 70.317 % | differs |
| Commercial site: Wet Detention removal, nitrogen | 42.607 % | 38.347 % | differs |
| Commercial site: Wet Detention removal, phosphorus | 78.130 % | 70.317 % | differs |
BMPFast 2 gives a different number for: Nitrogen leaving the site, Phosphorus leaving the site, Site removal, nitrogen, Site removal, phosphorus, Commercial site: Wet Detention removal, nitrogen, Commercial site: Wet Detention removal, phosphorus. See the notes below the table.
When BMPFast 2 opened the v1 file it said:
- Commercial site, Wet Detention: BMPFast 2 takes the wet pond equations as a pond without a littoral zone, and this pond has none, so its removal is not multiplied by 0.90 as v1 does: it is higher than v1 shows. To calculate as v1, choose "Reduce without a littoral zone (v1)" in How the littoral zone counts (Design values) on the treatment's Entry tab.
4Check
Runoff and loads (Equations 9-1 and 9-2 of AH Vol I).
| Runoff | = ROC × area × rainfall / 12 |
| = 0.596 × 5.00 ac × 54.0 in / 12 | |
| = 13.410 ac-ft/yr (program 13.410). |
| TN load | = EMC × runoff × 1.233 |
| = 2.400 × 13.410 × 1.233 | |
| = 39.683 kg/yr (program 39.683) |
| TP load | = 0.345 × 13.410 × 1.233 |
| = 5.704 kg/yr (program 5.704). |
1.233 kg is 1 mg/L in 1 ac-ft.
Annual residence time.
| ART | = permanent pool × 365 / annual runoff |
| = 6.000 ac-ft × 365 / 13.410 ac-ft/yr | |
| = 163.3 days (program 163.3). |
Removal. The wet detention equations of AH Vol I Appendix O at 163.3 days, without a littoral zone, so BMPFast 2 gives the equations’ removal with no credit (BMPFast v1 multiplies it by 0.90), give TN 42.61 % and TP 78.13 %. The worksheet’s Equations page shows each equation with these numbers; the Wet Detention Methodology explains them.
Load out.
| TN out | = load in × (1 − removal) |
| = 39.683 × (1 − 42.61 / 100) | |
| = 22.775 kg/yr (program 22.775) |
| TP out | = 5.704 × (1 − 78.13 / 100) |
| = 1.248 kg/yr (program 1.248). |
The standard is not met, and that is expected. “Impaired Water” requires 80 % TN and 80 % TP, and the post-development load not above the pre-development load, for a discharge to an impaired water (AH Vol I 8.3.4(a)). The post = pre removal (Equation 9-3, (post load − pre load) / post load) is TN 94.1 % and TP 98.4 %. BMPFast takes the larger of the standard’s percentage and the post = pre removal as the Maximum % Removal, shown on every worksheet’s status bar and in the Summary Report: here TN 94.1 % and TP 98.4 %. This problem shows what this design removes (42.6 % / 78.1 %), which is less. To meet it, add BMPs in series or downstream catchments (see BMPs in Series and Routing), or size the BMP (see Sizing).
The program’s Equations page
5Files
- wet-detention-impaired.bmpf: the project, saved by BMPFast 2. Save it (your browser puts it in Downloads), then in BMPFast 2 choose File ▸ Open and open it. Opened again and calculated, it gives the numbers on this page.
- wet-detention-impaired.bmpt: the same project as BMPFast (v1) saved it. BMPFast 2 opens it too (File ▸ Open); saving it then makes a .bmpf and leaves the .bmpt as it was.
- Routing 1 (BMPFast 2’s report, as Open in browser on its Report tab gives it)
- Routing 1 — Summary Report (BMPFast 2’s report, as Open in browser on its Report tab gives it)
- Wet Detention (BMPFast 2’s report, as Open in browser on its Report tab gives it)
- Wet Detention — calculations (BMPFast 2’s report, as Open in browser on its Report tab gives it)
6Help and methodology
Calculated with BMPFast 2 version 2.0.0 (2026-10-20), which opens the problem’s v1 project as it is. Screen captures are of BMPFast 2’s own window and are for demonstration only.