SoftwarePlus.ai

All programs › BMPFast › BMPFast 2 sample problems

Wet detention for a commercial site discharging to an impaired water

A 6.0 ac-ft pool, no littoral zone; Impaired Water, Zone 3.

1The problem

A 5-acre high-intensity commercial site on former flatwoods discharges to an impaired water. Its wet pond has a 6.0 ac-ft permanent pool and no littoral zone.

InputValueSource
Project (General Site Information)
Meteorological zoneFlorida Zone 3Zone map (help page 815)
Mean annual rainfall54 inMean annual rainfall map (help page 815)
Performance standard (analysis type)Impaired WaterSite (illustrative)
Catchment 1: Commercial site (Watershed Characteristics)
Land use, pre / postUndeveloped - Mesic Flatwoods / High-Intensity CommercialSite (illustrative)
Area, pre / post5 / 5 acSite (illustrative)
Non-DCIA curve number, pre / post70 / 80Site (illustrative)
DCIA, pre / post0 / 70 %Site (illustrative)
EMC TN, pre / post1.087 / 2.400 mg/LBMPFast land use table (AH Vol I Table 9.2)
EMC TP, pre / post0.043 / 0.345 mg/LBMPFast land use table (AH Vol I Table 9.2)
Wet Detention (worksheet)
Permanent Pool Volume6.0 ac-ftDesign (illustrative)
There is a littoral zoneuntickedDesign (illustrative)
Floating Wetland or other MAPs Credit0 %Design (illustrative)

Find: the TN and TP removal of the BMP, the loads leaving the site, and whether the performance standard is met.

2Steps in BMPFast 2

  1. Start BMPFast 2 and choose File ▸ New project. The tree on the left opens on the project (General Site Information). On its Entry tab enter: Project name Wet detention: commercial site, impaired water; Meteorological zone Florida Zone 3; Mean annual rainfall 54.00 in; Type of analysis Impaired Water. (To follow along with the finished project instead, choose File ▸ Open and open wet-detention-impaired.bmpf from Files below.)

    General Site Information: the project’s Entry tab.
    General Site Information: the project’s Entry tab.
  2. Press Add Catchment (left). Select the new catchment in the tree; on its Entry tab type the name Commercial site and enter: Land use (pre) Undeveloped - Mesic Flatwoods; Land use (post) High-Intensity Commercial; Area (pre) 5.00 ac; Area (post) 5.00 ac; Non-DCIA curve number (pre) 70.00; Non-DCIA curve number (post) 80.00; DCIA (post) 70.00 %. Leave the other boxes as they are (0 or blank). BMPFast 2 calculates as you type; scroll down to Calculated for the results after development: Annual runoff coefficient (ROC) (post) 0.596; Runoff volume (post) 13.410 ac-ft/yr; Nitrogen load (post) 39.683 kg/yr; Phosphorus load (post) 5.704 kg/yr.

    The catchment Commercial site: its Entry tab.
    The catchment Commercial site: its Entry tab.
  3. With Commercial site selected, press Add Treatment and choose Wet Detention. On its Entry tab type the Treatment name Wet Detention (BMPFast 2 starts it as “Wet Detention 1”) and enter: Permanent pool volume 6.000 ac-ft; How the littoral zone counts Littoral zone credit (BMPFast 2). The results are calculated as you type: Average residence time 163.31 days; Permanent pool volume for 31 days residence 1.14 ac-ft; Nitrogen removal provided 42.61 %; Phosphorus removal provided 78.13 %.

    The treatment Wet Detention: its Entry tab.
    The treatment Wet Detention: its Entry tab.
  4. Open the treatment’s Report tab: its inputs and removal, as a report to print or save.

    The treatment Wet Detention: its Report tab.
    The treatment Wet Detention: its Report tab.
  5. Press Add Routing (left). BMPFast 2 adds Routing 1 under Catchment Routings, with every catchment draining to the outlet and no treatment; a project can have several routings, compared side by side. On its Entry tab (How the routing is calculated Strand routing (v1's routing; use this for permits)) set each catchment as in this table:

    CatchmentDrains toTreatment used
    Commercial siteOutletWet Detention

    A catchment is treated only by the treatment its routing uses.

    The routing’s Entry tab: where each catchment drains and the treatment it uses.
    The routing’s Entry tab: where each catchment drains and the treatment it uses.
  6. Open the routing’s Report tab. Results shows the loads leaving the site, the removal provided and required, and whether the performance standard is met; the list at the top of the tab has v1’s reports for the same routing (Summary, Complete, Flow Balance, AH Vol I Sec 9 compliance). Save the project with File ▸ Save; compare it with the .bmpf under Files.

    The routing’s Report tab: Results.
    The routing’s Report tab: Results.

3Results

ResultValue
Catchment 1: computed by BMPFast
Annual runoff coefficient (ROC), pre / post0.078 / 0.596
Runoff, pre / post1.755 / 13.410 ac-ft/yr
TN load, pre / post2.352 / 39.683 kg/yr
TP load, pre / post0.093 / 5.704 kg/yr
Wet Detention: computed by BMPFast
Annual residence time163.3 days
Hydraulic capture efficiency70.00 %
Provided TN / TP removal42.61 % / 78.13 %
TN load in → out39.683 → 22.775 kg/yr
TP load in → out5.704 → 1.248 kg/yr
Site (all catchments, at the outlet)
TN load: catchments → outlet39.683 → 22.775 kg/yr
TP load: catchments → outlet5.704 → 1.248 kg/yr
Provided removal TN / TP42.6 % / 78.1 %
Required removal TN / TP (Maximum % Removal)94.1 % (not met) / 98.4 % (not met)

The BMP report

Open this report on its own page.

The Summary Report

Open this report on its own page.

BMPFast 2 and BMPFast (v1)

ResultBMPFast 2BMPFast (v1), its page
Nitrogen leaving the site22.775 kg/yr24.466 kg/yrdiffers
Phosphorus leaving the site1.248 kg/yr1.693 kg/yrdiffers
Site removal, nitrogen42.607 %38.347 %differs
Site removal, phosphorus78.130 %70.317 %differs
Commercial site: Wet Detention removal, nitrogen42.607 %38.347 %differs
Commercial site: Wet Detention removal, phosphorus78.130 %70.317 %differs

BMPFast 2 gives a different number for: Nitrogen leaving the site, Phosphorus leaving the site, Site removal, nitrogen, Site removal, phosphorus, Commercial site: Wet Detention removal, nitrogen, Commercial site: Wet Detention removal, phosphorus. See the notes below the table.

When BMPFast 2 opened the v1 file it said:

  • Commercial site, Wet Detention: BMPFast 2 takes the wet pond equations as a pond without a littoral zone, and this pond has none, so its removal is not multiplied by 0.90 as v1 does: it is higher than v1 shows. To calculate as v1, choose "Reduce without a littoral zone (v1)" in How the littoral zone counts (Design values) on the treatment's Entry tab.

4Check

Runoff and loads (Equations 9-1 and 9-2 of AH Vol I).

1.233 kg is 1 mg/L in 1 ac-ft.

Annual residence time.

Removal. The wet detention equations of AH Vol I Appendix O at 163.3 days, without a littoral zone, so BMPFast 2 gives the equations’ removal with no credit (BMPFast v1 multiplies it by 0.90), give TN 42.61 % and TP 78.13 %. The worksheet’s Equations page shows each equation with these numbers; the Wet Detention Methodology explains them.

Load out.

The standard is not met, and that is expected. “Impaired Water” requires 80 % TN and 80 % TP, and the post-development load not above the pre-development load, for a discharge to an impaired water (AH Vol I 8.3.4(a)). The post = pre removal (Equation 9-3, (post load − pre load) / post load) is TN 94.1 % and TP 98.4 %. BMPFast takes the larger of the standard’s percentage and the post = pre removal as the Maximum % Removal, shown on every worksheet’s status bar and in the Summary Report: here TN 94.1 % and TP 98.4 %. This problem shows what this design removes (42.6 % / 78.1 %), which is less. To meet it, add BMPs in series or downstream catchments (see BMPs in Series and Routing), or size the BMP (see Sizing).

The program’s Equations page

Open this report on its own page.

5Files

  • wet-detention-impaired.bmpf: the project, saved by BMPFast 2. Save it (your browser puts it in Downloads), then in BMPFast 2 choose File ▸ Open and open it. Opened again and calculated, it gives the numbers on this page.
  • wet-detention-impaired.bmpt: the same project as BMPFast (v1) saved it. BMPFast 2 opens it too (File ▸ Open); saving it then makes a .bmpf and leaves the .bmpt as it was.
  • Routing 1 (BMPFast 2’s report, as Open in browser on its Report tab gives it)
  • Routing 1 — Summary Report (BMPFast 2’s report, as Open in browser on its Report tab gives it)
  • Wet Detention (BMPFast 2’s report, as Open in browser on its Report tab gives it)
  • Wet Detention — calculations (BMPFast 2’s report, as Open in browser on its Report tab gives it)

6Help and methodology

Calculated with BMPFast 2 version 2.0.0 (2026-10-20), which opens the problem’s v1 project as it is. Screen captures are of BMPFast 2’s own window and are for demonstration only.