All programs › BMPFast › BMPFast 2 sample problems
Wet detention pond with a littoral zone
A 4.0 ac-ft permanent pool with a littoral zone; All sites non-exempted, Zone 2.
Help: Wet Detention (help page 211) · Download the .bmpf · Link to Solution in BMPFast Version 1
1The problem
The same 10-acre subdivision drains to a wet detention pond with a permanent pool of 4.0 ac-ft and a littoral zone.
| Input | Value | Source |
|---|---|---|
| Project (General Site Information) | ||
| Meteorological zone | Florida Zone 2 | Zone map (help page 815) |
| Mean annual rainfall | 50 in | Mean annual rainfall map (help page 815) |
| Performance standard (analysis type) | All sites non-exempted | Site (illustrative) |
| Catchment 1: Subdivision (Watershed Characteristics) | ||
| Land use, pre / post | Agricultural - Pasture / Single-Family | Site (illustrative) |
| Area, pre / post | 10 / 10 ac | Site (illustrative) |
| Non-DCIA curve number, pre / post | 61 / 75 | Site (illustrative) |
| DCIA, pre / post | 0 / 25 % | Site (illustrative) |
| EMC TN, pre / post | 3.030 / 1.770 mg/L | BMPFast land use table (AH Vol I Table 9.2) |
| EMC TP, pre / post | 0.593 / 0.327 mg/L | BMPFast land use table (AH Vol I Table 9.2) |
| Wet Detention (worksheet) | ||
| Permanent Pool Volume | 4.0 ac-ft | Design (illustrative) |
| There is a littoral zone | ticked | Design (illustrative) |
| Floating Wetland or other MAPs Credit | 0 % | Design (illustrative) |
Find: the TN and TP removal of the BMP, the loads leaving the site, and whether the performance standard is met.
2Steps in BMPFast 2
Start BMPFast 2 and choose File ▸ New project. The tree on the left opens on the project (General Site Information). On its Entry tab enter: Project name Wet detention: 10 ac subdivision; Meteorological zone Florida Zone 2; Mean annual rainfall 50.00 in; Type of analysis All sites non-exempted. (To follow along with the finished project instead, choose File ▸ Open and open
wet-detention-littoral.bmpffrom Files below.)
General Site Information: the project’s Entry tab. Press Add Catchment (left). Select the new catchment in the tree; on its Entry tab type the name Subdivision and enter: Land use (pre) Agricultural - Pasture; Land use (post) Single-Family; Area (pre) 10.00 ac; Area (post) 10.00 ac; Non-DCIA curve number (pre) 61.00; Non-DCIA curve number (post) 75.00; DCIA (post) 25.00 %. Leave the other boxes as they are (0 or blank). BMPFast 2 calculates as you type; scroll down to Calculated for the results after development: Annual runoff coefficient (ROC) (post) 0.262; Runoff volume (post) 10.917 ac-ft/yr; Nitrogen load (post) 23.825 kg/yr; Phosphorus load (post) 4.402 kg/yr.

The catchment Subdivision: its Entry tab. With Subdivision selected, press Add Treatment and choose Wet Detention. On its Entry tab type the Treatment name Wet Detention (BMPFast 2 starts it as “Wet Detention 1”) and enter: Permanent pool volume 4.000 ac-ft; How the littoral zone counts Littoral zone credit (BMPFast 2); There is a littoral zone Yes; Littoral zone credit 10.0 %. The results are calculated as you type: Average residence time 133.74 days; Permanent pool volume for 31 days residence 0.93 ac-ft; Nitrogen removal provided 52.36 %; Phosphorus removal provided 86.43 %.

The treatment Wet Detention: its Entry tab. Open the treatment’s Report tab: its inputs and removal, as a report to print or save.

The treatment Wet Detention: its Report tab. Press Add Routing (left). BMPFast 2 adds Routing 1 under Catchment Routings, with every catchment draining to the outlet and no treatment; a project can have several routings, compared side by side. On its Entry tab (How the routing is calculated Strand routing (v1's routing; use this for permits)) set each catchment as in this table:
Catchment Drains to Treatment used Subdivision Outlet Wet Detention A catchment is treated only by the treatment its routing uses.

The routing’s Entry tab: where each catchment drains and the treatment it uses. Open the routing’s Report tab. Results shows the loads leaving the site, the removal provided and required, and whether the performance standard is met; the list at the top of the tab has v1’s reports for the same routing (Summary, Complete, Flow Balance, AH Vol I Sec 9 compliance). Save the project with File ▸ Save; compare it with the .bmpf under Files.

The routing’s Report tab: Results.
3Results
| Result | Value |
|---|---|
| Catchment 1: computed by BMPFast | |
| Annual runoff coefficient (ROC), pre / post | 0.032 / 0.262 |
| Runoff, pre / post | 1.350 / 10.917 ac-ft/yr |
| TN load, pre / post | 5.044 / 23.825 kg/yr |
| TP load, pre / post | 0.987 / 4.402 kg/yr |
| Wet Detention: computed by BMPFast | |
| Annual residence time | 133.7 days |
| Hydraulic capture efficiency | 76.00 % |
| Provided TN / TP removal | 52.36 % / 86.43 % |
| TN load in → out | 23.825 → 11.349 kg/yr |
| TP load in → out | 4.402 → 0.597 kg/yr |
| Site (all catchments, at the outlet) | |
| TN load: catchments → outlet | 23.825 → 11.349 kg/yr |
| TP load: catchments → outlet | 4.402 → 0.597 kg/yr |
| Provided removal TN / TP | 52.4 % / 86.4 % |
| Required removal TN / TP (Maximum % Removal) | 78.8 % (not met) / 80.0 % (met) |
The BMP report
Open this report on its own page.
The Summary Report
Open this report on its own page.
BMPFast 2 and BMPFast (v1)
| Result | BMPFast 2 | BMPFast (v1), its page | |
|---|---|---|---|
| Nitrogen leaving the site | 11.349 kg/yr | 13.732 kg/yr | differs |
| Phosphorus leaving the site | 0.597 kg/yr | 1.037 kg/yr | differs |
| Site removal, nitrogen | 52.363 % | 42.363 % | differs |
| Site removal, phosphorus | 86.432 % | 76.432 % | differs |
| Subdivision: Wet Detention removal, nitrogen | 52.363 % | 42.363 % | differs |
| Subdivision: Wet Detention removal, phosphorus | 86.432 % | 76.432 % | differs |
BMPFast 2 gives a different number for: Nitrogen leaving the site, Phosphorus leaving the site, Site removal, nitrogen, Site removal, phosphorus, Subdivision: Wet Detention removal, nitrogen, Subdivision: Wet Detention removal, phosphorus. See the notes below the table.
When BMPFast 2 opened the v1 file it said:
- Subdivision, Wet Detention: BMPFast 2 takes the wet pond equations as a pond without a littoral zone, and adds a littoral zone credit of 10 percentage points (Appendix O's maximum) to this pond's removal, so it is higher than v1 shows; lower Littoral zone credit if your permit reviewer allows less. To calculate as v1, choose "Reduce without a littoral zone (v1)" in How the littoral zone counts (Design values) on the treatment's Entry tab.
4Check
Runoff and loads (Equations 9-1 and 9-2 of AH Vol I).
| Runoff | = ROC × area × rainfall / 12 |
| = 0.262 × 10.00 ac × 50.0 in / 12 | |
| = 10.917 ac-ft/yr (program 10.917). |
| TN load | = EMC × runoff × 1.233 |
| = 1.770 × 10.917 × 1.233 | |
| = 23.825 kg/yr (program 23.825) |
| TP load | = 0.327 × 10.917 × 1.233 |
| = 4.402 kg/yr (program 4.402). |
1.233 kg is 1 mg/L in 1 ac-ft.
Annual residence time.
| ART | = permanent pool × 365 / annual runoff |
| = 4.000 ac-ft × 365 / 10.917 ac-ft/yr | |
| = 133.7 days (program 133.7). |
Removal. The wet detention equations of AH Vol I Appendix O at 133.7 days (TN 42.36 %, TP 76.43 %), with the littoral zone credit of 10 percentage points added to each because the pond has a littoral zone (BMPFast 2 takes the equations as a pond without one), give TN 52.36 % and TP 86.43 %. The worksheet’s Equations page shows each equation with these numbers; the Wet Detention Methodology explains them.
Load out.
| TN out | = load in × (1 − removal) |
| = 23.825 × (1 − 52.36 / 100) | |
| = 11.349 kg/yr (program 11.349) |
| TP out | = 4.402 × (1 − 86.43 / 100) |
| = 0.597 kg/yr (program 0.597). |
The standard is not met, and that is expected. “All sites non-exempted” requires the greater of 55 % TN and 80 % TP, or the removal that keeps the post-development load at the pre-development load (Equation 9-3) (AH Vol I 8.3.2). The post = pre removal (Equation 9-3, (post load − pre load) / post load) is TN 78.8 % and TP 77.6 %. BMPFast takes the larger of the standard’s percentage and the post = pre removal as the Maximum % Removal, shown on every worksheet’s status bar and in the Summary Report: here TN 78.8 % and TP 80.0 %. This problem shows what this design removes (52.4 % / 86.4 %), which is less. To meet it, add BMPs in series or downstream catchments (see BMPs in Series and Routing), or size the BMP (see Sizing).
The program’s Equations page
5Files
- wet-detention-littoral.bmpf: the project, saved by BMPFast 2. Save it (your browser puts it in Downloads), then in BMPFast 2 choose File ▸ Open and open it. Opened again and calculated, it gives the numbers on this page.
- wet-detention-littoral.bmpt: the same project as BMPFast (v1) saved it. BMPFast 2 opens it too (File ▸ Open); saving it then makes a .bmpf and leaves the .bmpt as it was.
- Routing 1 (BMPFast 2’s report, as Open in browser on its Report tab gives it)
- Routing 1 — Summary Report (BMPFast 2’s report, as Open in browser on its Report tab gives it)
- Wet Detention (BMPFast 2’s report, as Open in browser on its Report tab gives it)
- Wet Detention — calculations (BMPFast 2’s report, as Open in browser on its Report tab gives it)
6Help and methodology
Calculated with BMPFast 2 version 2.0.0 (2026-10-20), which opens the problem’s v1 project as it is. Screen captures are of BMPFast 2’s own window and are for demonstration only.