All programs › BMPFast › Sample problems
Greenroof on an office building
Half an acre of greenroof, no cistern, Orlando; BMP Analysis.
Help: Greenroof (help page 288) · Download the .bmpt · Link to Solution in BMPFast Version 2
1The problem
A half-acre office roof in Orlando is built as a greenroof. Its filtrate is not stored (no cistern).
| Input | Value | Source |
|---|---|---|
| Project (General Site Information) | ||
| Meteorological zone | Florida Zone 2 | Zone map (help page 815) |
| Mean annual rainfall | 50 in | Mean annual rainfall map (help page 815) |
| Performance standard (analysis type) | BMP Analysis | Site (illustrative) |
| Catchment 1: Office roof (Watershed Characteristics) | ||
| Land use, pre / post | Undeveloped - Mesic Flatwoods / Conventional Roofs | Site (illustrative) |
| Area, pre / post | 0.5 / 0.5 ac | Site (illustrative) |
| Non-DCIA curve number, pre / post | 70 / 98 | Site (illustrative) |
| DCIA, pre / post | 0 / 100 % | Site (illustrative) |
| EMC TN, pre / post | 1.087 / 1.050 mg/L | BMPFast land use table (AH Vol I Table 9.2) |
| EMC TP, pre / post | 0.043 / 0.120 mg/L | BMPFast land use table (AH Vol I Table 9.2) |
| Greenroof (worksheet) | ||
| Rainfall station | Orlando #6628 | Design (illustrative) |
| Greenroof area | 21780 sf | Design (illustrative) |
| Cistern storage over greenroof area | 0 in | Design (illustrative) |
| Irrigation demand | 0 in/yr | Design (illustrative) |
| Rainfall excess (filtrate underdrain flow) | 0 in/yr | Design (illustrative) |
Find: the TN and TP removal of the BMP, the loads leaving the site, and whether the performance standard is met.
2Steps in BMPFast
Press New Project. On General Site Information (the main window; its title bar reads General Site Information and your license key) type the project name Greenroof: office roof, no cistern, choose Florida Zone 2, enter 50 in of mean annual rainfall and choose the performance standard BMP Analysis.

General Site Information (the main window). Press 1. Enter Catchment. For Catchment 1 type the name Office roof, choose the land uses Undeveloped - Mesic Flatwoods (pre) and Conventional Roofs (post), enter the areas 0.5 and 0.5 ac, the non-DCIA curve numbers 70 and 98 and the DCIA 0 and 100 %, then press Calculate. BMPFast shows the annual runoff coefficient, the runoff and the TN and TP loads. Press Back.

Watershed Characteristics Worksheet (1. Enter Catchment). Press 2. Enter Treatment and then Greenroof. On the Greenroof worksheet: Rainfall station Orlando #6628; Greenroof area 21780 sf; Cistern storage over greenroof area 0 in; Irrigation demand 0 in/yr; Rainfall excess (filtrate underdrain flow) 0 in/yr. Press Calculate. The report on the worksheet shows the inputs and the results.

The BMP worksheet after Calculate: the report on the left. Press the same button again, now labelled Equations: the worksheet shows each equation with this problem’s values. Press Back to return to the treatment options.

The same worksheet showing Equations: each equation with this problem’s values. On the main window press 3. Configure Catchments and double-click Catchment 1. Choose Greenroof as the BMP used in routing and the Outlet as where it goes. Press Back twice. (A catchment’s BMP is only used once it is chosen here.)

Routing for Catchment 1 (3. Configure Catchments): the BMP used and where the catchment goes. Press 4. Summary Report. The Report Viewer shows the loads, the removal and whether the performance standard is met. Press Save Project to keep your copy; compare it with the .bmpt under Files.

The Summary Report (4. Summary Report) in the Report Viewer.
3Results
| Result | Value |
|---|---|
| Catchment 1: computed by BMPFast | |
| Annual runoff coefficient (ROC), pre / post | 0.057 / 0.809 |
| Runoff, pre / post | 0.119 / 1.685 ac-ft/yr |
| TN load, pre / post | 0.159 / 2.182 kg/yr |
| TP load, pre / post | 0.006 / 0.249 kg/yr |
| Greenroof: computed by BMPFast | |
| Hydraulic capture efficiency | 43.00 % |
| Provided TN / TP removal | 43.00 % / 43.00 % |
| TN load in → out | 2.182 → 1.244 kg/yr |
| TP load in → out | 0.249 → 0.142 kg/yr |
| Site (all catchments, at the outlet) | |
| TN load: catchments → outlet | 2.182 → 1.244 kg/yr |
| TP load: catchments → outlet | 0.249 → 0.142 kg/yr |
| Provided removal TN / TP | 43.0 % / 43.0 % |
The BMP report
Open this report on its own page.
The Summary Report
4Check
Runoff and loads (Equations 9-1 and 9-2 of AH Vol I).
| Runoff | = ROC × area × rainfall / 12 |
| = 0.809 × 0.50 ac × 50.0 in / 12 | |
| = 1.685 ac-ft/yr (program 1.685). |
| TN load | = EMC × runoff × 1.233 |
| = 1.050 × 1.685 × 1.233 | |
| = 2.182 kg/yr (program 2.182) |
| TP load | = 0.120 × 1.685 × 1.233 |
| = 0.249 kg/yr (program 0.249). |
1.233 kg is 1 mg/L in 1 ac-ft.
Capture. With no cistern the greenroof alone retains 43.00 % of the annual runoff (the program’s greenroof value for Orlando #6628). The water that stays on the roof keeps its nitrogen and phosphorus, so the TN and TP removal equal the capture (Harvesting and Greenroof Methodology).
Load out.
| TN out | = load in × (1 − removal) |
| = 2.182 × (1 − 43.00 / 100) | |
| = 1.244 kg/yr (program 1.244) |
| TP out | = 0.249 × (1 − 43.00 / 100) |
| = 0.142 kg/yr (program 0.142). |
The program’s Equations page
5Files
- greenroof-no-cistern.bmpt: the project, saved by BMPFast. Save it (your browser puts it in Downloads). In BMPFast press Open Project, then Open Project again in the Open BMPFast Project dialog (below its Recent Projects list), and choose the file.
- Equations page (worksheet) (as BMPFast shows it)
- Summary Report (as BMPFast shows it)
- BMP report (worksheet) (as BMPFast shows it)
6Help and methodology
Calculated with BMPFast 1.1.9 (build 6.0.0, 2026-10-16). Older versions may not have the Equations button or may give slightly different results; download the latest at bmpfast.com. Screen captures are for demonstration only.