Detention rain garden with an underdrain
A rain garden with an underdrain and B&G CTS12 media; Net Improvement, Zone 4.
Help: Rain Garden (help page 312) · Download the .bmpt · Link to Solution in BMPFast Version 2
1The problem
A 1-acre townhome site drains to a rain garden with an underdrain (detention): what it filters through B&G CTS12 media is discharged.
| Input | Value | Source |
|---|---|---|
| Project (General Site Information) | ||
| Meteorological zone | Florida Zone 4 | Zone map (help page 815) |
| Mean annual rainfall | 52 in | Mean annual rainfall map (help page 815) |
| Performance standard (analysis type) | Net Improvement | Site (illustrative) |
| Catchment 1: Townhomes (Watershed Characteristics) | ||
| Land use, pre / post | Agricultural - Pasture / Multi-Family | Site (illustrative) |
| Area, pre / post | 1 / 1 ac | Site (illustrative) |
| Non-DCIA curve number, pre / post | 61 / 80 | Site (illustrative) |
| DCIA, pre / post | 0 / 50 % | Site (illustrative) |
| EMC TN, pre / post | 3.030 / 1.840 mg/L | BMPFast land use table (AH Vol I Table 9.2) |
| EMC TP, pre / post | 0.593 / 0.520 mg/L | BMPFast land use table (AH Vol I Table 9.2) |
| Media mix | B&G CTS12 (TN 60 %, TP 90 %) | BMPFast media table (help page 817) |
| Rain Garden Analysis (worksheet) | ||
| System Type | Detention | Design (illustrative) |
| Sustainable Void Fraction | 0.3 | Design (illustrative) |
| Native Soil Volume | 2000 cubic feet | Design (illustrative) |
| Water Storage above Media | 1000 cubic feet | Design (illustrative) |
| Credit for Native Soil and Cover Crop | 0 % | Design (illustrative) |
Find: the TN and TP removal of the BMP, the loads leaving the site, and whether the performance standard is met.
2Steps in BMPFast
Press New Project. On General Site Information (the main window; its title bar reads General Site Information and your license key) type the project name Rain garden: detention with underdrain, choose Florida Zone 4, enter 52 in of mean annual rainfall and choose the performance standard Net Improvement.

General Site Information (the main window). Press 1. Enter Catchment. For Catchment 1 type the name Townhomes, choose the land uses Agricultural - Pasture (pre) and Multi-Family (post), enter the areas 1 and 1 ac, the non-DCIA curve numbers 61 and 80 and the DCIA 0 and 50 %, then press Calculate. BMPFast shows the annual runoff coefficient, the runoff and the TN and TP loads. Press Back.

Watershed Characteristics Worksheet (1. Enter Catchment). Press 2. Enter Treatment, then Rain Garden, and on its worksheet press Media. Choose B&G CTS12 (TN 60 %, TP 90 % when all the runoff is treated) and press Back.

Enter Media Mix Information (the Media button). Press 2. Enter Treatment and then Rain Garden. On the Rain Garden Analysis worksheet: System Type Detention; Sustainable Void Fraction 0.3; Native Soil Volume 2000 cubic feet; Water Storage above Media 1000 cubic feet; Credit for Native Soil and Cover Crop 0 %. Press Calculate. The report on the worksheet shows the inputs and the results.

The BMP worksheet after Calculate: the report on the left. Press the same button again, now labelled Equations: the worksheet shows each equation with this problem’s values. Press Back to return to the treatment options.

The same worksheet showing Equations: each equation with this problem’s values. On the main window press 3. Configure Catchments and double-click Catchment 1. Choose Rain Garden as the BMP used in routing and the Outlet as where it goes. Press Back twice. (A catchment’s BMP is only used once it is chosen here.)

Routing for Catchment 1 (3. Configure Catchments): the BMP used and where the catchment goes. Press 4. Summary Report. The Report Viewer shows the loads, the removal and whether the performance standard is met. Press Save Project to keep your copy; compare it with the .bmpt under Files.

The Summary Report (4. Summary Report) in the Report Viewer.
3Results
| Result | Value |
|---|---|
| Catchment 1: computed by BMPFast | |
| Annual runoff coefficient (ROC), pre / post | 0.043 / 0.476 |
| Runoff, pre / post | 0.185 / 2.063 ac-ft/yr |
| TN load, pre / post | 0.693 / 4.680 kg/yr |
| TP load, pre / post | 0.136 / 1.322 kg/yr |
| Rain Garden: computed by BMPFast | |
| Treatment depth | 0.441 in |
| Provided TN / TP removal | 60.00 % / 90.00 % |
| TN load in → out | 4.680 → 1.872 kg/yr |
| TP load in → out | 1.322 → 0.132 kg/yr |
| Site (all catchments, at the outlet) | |
| TN load: catchments → outlet | 4.680 → 1.872 kg/yr |
| TP load: catchments → outlet | 1.322 → 0.132 kg/yr |
| Provided removal TN / TP | 60.0 % / 90.0 % |
| Required removal TN / TP (Maximum % Removal) | 85.2 % (not met) / 89.7 % (met) |
The BMP report
Open this report on its own page.
The Summary Report
4Check
Runoff and loads (Equations 9-1 and 9-2 of AH Vol I).
| Runoff | = ROC × area × rainfall / 12 |
| = 0.476 × 1.00 ac × 52.0 in / 12 | |
| = 2.063 ac-ft/yr (program 2.063). |
| TN load | = EMC × runoff × 1.233 |
| = 1.840 × 2.063 × 1.233 | |
| = 4.680 kg/yr (program 4.680) |
| TP load | = 0.520 × 2.063 × 1.233 |
| = 1.322 kg/yr (program 1.322). |
1.233 kg is 1 mg/L in 1 ac-ft.
Storage.
| Storage | = native soil volume × void fraction + water above the media |
| = 2,000 × 0.30 + 1,000 | |
| = 1,600 cf (program 1,600). |
Treatment depth.
| Depth | = storage × 12 / area |
| = 0.0367 ac-ft × 12 / 1.00 ac | |
| = 0.441 in (program 0.441). |
Removal. A detention rain garden discharges what it filters, so its removal is the media reduction of B&G CTS12: TN 60 %, TP 90 % (program 60.00 / 90.00).
Load out.
| TN out | = load in × (1 − removal) |
| = 4.680 × (1 − 60.00 / 100) | |
| = 1.872 kg/yr (program 1.872) |
| TP out | = 1.322 × (1 − 90.00 / 100) |
| = 0.132 kg/yr (program 0.132). |
The standard is not met, and that is expected. “Net Improvement” requires only that the post-development load is not above the pre-development load (Equation 9-3) (AH Vol I 8.2.3 and 8.3.4(a)3). The post = pre removal (Equation 9-3, (post load − pre load) / post load) is TN 85.2 % and TP 89.7 %. BMPFast takes the larger of the standard’s percentage and the post = pre removal as the Maximum % Removal, shown on every worksheet’s status bar and in the Summary Report: here TN 85.2 % and TP 89.7 %. This problem shows what this design removes (60.0 % / 90.0 %), which is less. To meet it, add BMPs in series or downstream catchments (see BMPs in Series and Routing), or size the BMP (see Sizing).
The program’s Equations page
5Files
- rain-garden-detention.bmpt: the project, saved by BMPFast. Save it (your browser puts it in Downloads). In BMPFast press Open Project, then Open Project again in the Open BMPFast Project dialog (below its Recent Projects list), and choose the file.
- Equations page (worksheet) (as BMPFast shows it)
- Summary Report (as BMPFast shows it)
- BMP report (worksheet) (as BMPFast shows it)
6Help and methodology
Calculated with BMPFast 1.1.9 (build 6.0.0, 2026-10-16). Older versions may not have the Equations button or may give slightly different results; download the latest at bmpfast.com. Screen captures are for demonstration only.