All programs › BMPFast › Sample problems
Rainwater harvesting at a school
A 30,000-gallon cistern on a flat concrete roof; Redevelopment + OFW, Zone 3.
Help: Rainwater Harvesting (help page 292) · Download the .bmpt · Link to Solution in BMPFast Version 2
1The problem
A 1-acre flat concrete school roof fills a 30,000-gallon cistern that irrigates 2 acres of fields at 1.5 in/week.
| Input | Value | Source |
|---|---|---|
| Project (General Site Information) | ||
| Meteorological zone | Florida Zone 3 | Zone map (help page 815) |
| Mean annual rainfall | 54 in | Mean annual rainfall map (help page 815) |
| Performance standard (analysis type) | Redevelopment + OFW | Site (illustrative) |
| Catchment 1: School roof (Watershed Characteristics) | ||
| Land use, pre / post | Undeveloped - Mesic Flatwoods / Conventional Roofs | Site (illustrative) |
| Area, pre / post | 1 / 1 ac | Site (illustrative) |
| Non-DCIA curve number, pre / post | 70 / 98 | Site (illustrative) |
| DCIA, pre / post | 0 / 100 % | Site (illustrative) |
| EMC TN, pre / post | 1.087 / 1.050 mg/L | BMPFast land use table (AH Vol I Table 9.2) |
| EMC TP, pre / post | 0.043 / 0.120 mg/L | BMPFast land use table (AH Vol I Table 9.2) |
| Rainwater Harvesting (worksheet) | ||
| Roof type | CONCRETE, 0.2% SLOPE | Design (illustrative) |
| Contributing area | 43560 sf | Design (illustrative) |
| Available harvest volume | 30000 gal | Design (illustrative) |
| Harvest rate | 1.5 in/week | Design (illustrative) |
| Area available for irrigation | 87120 sf | Design (illustrative) |
Find: the TN and TP removal of the BMP, the loads leaving the site, and whether the performance standard is met.
2Steps in BMPFast
Press New Project. On General Site Information (the main window; its title bar reads General Site Information and your license key) type the project name Rainwater harvesting: school, flat roof, choose Florida Zone 3, enter 54 in of mean annual rainfall and choose the performance standard Redevelopment + OFW.

General Site Information (the main window). Press 1. Enter Catchment. For Catchment 1 type the name School roof, choose the land uses Undeveloped - Mesic Flatwoods (pre) and Conventional Roofs (post), enter the areas 1 and 1 ac, the non-DCIA curve numbers 70 and 98 and the DCIA 0 and 100 %, then press Calculate. BMPFast shows the annual runoff coefficient, the runoff and the TN and TP loads. Press Back.

Watershed Characteristics Worksheet (1. Enter Catchment). Press 2. Enter Treatment and then Rainwater Harvesting. On the Rainwater Harvesting worksheet: Roof type CONCRETE, 0.2% SLOPE; Contributing area 43560 sf; Available harvest volume 30000 gal; Harvest rate 1.5 in/week; Area available for irrigation 87120 sf. Press Calculate. The report on the worksheet shows the inputs and the results.

The BMP worksheet after Calculate: the report on the left. Press the same button again, now labelled Equations: the worksheet shows each equation with this problem’s values. Press Back to return to the treatment options.

The same worksheet showing Equations: each equation with this problem’s values. On the main window press 3. Configure Catchments and double-click Catchment 1. Choose Rainwater Harvesting as the BMP used in routing and the Outlet as where it goes. Press Back twice. (A catchment’s BMP is only used once it is chosen here.)

Routing for Catchment 1 (3. Configure Catchments): the BMP used and where the catchment goes. Press 4. Summary Report. The Report Viewer shows the loads, the removal and whether the performance standard is met. Press Save Project to keep your copy; compare it with the .bmpt under Files.

The Summary Report (4. Summary Report) in the Report Viewer.
3Results
| Result | Value |
|---|---|
| Catchment 1: computed by BMPFast | |
| Annual runoff coefficient (ROC), pre / post | 0.078 / 0.795 |
| Runoff, pre / post | 0.351 / 3.578 ac-ft/yr |
| TN load, pre / post | 0.470 / 4.632 kg/yr |
| TP load, pre / post | 0.019 / 0.529 kg/yr |
| Rainwater Harvesting: computed by BMPFast | |
| Hydraulic capture efficiency | 84.62 % |
| Provided TN / TP removal | 84.62 % / 84.62 % |
| TN load in → out | 4.632 → 0.713 kg/yr |
| TP load in → out | 0.529 → 0.081 kg/yr |
| Site (all catchments, at the outlet) | |
| TN load: catchments → outlet | 4.632 → 0.713 kg/yr |
| TP load: catchments → outlet | 0.529 → 0.081 kg/yr |
| Provided removal TN / TP | 84.6 % / 84.6 % |
| Required removal TN / TP (Maximum % Removal) | 60.0 % (met) / 90.0 % (not met) |
The BMP report
Open this report on its own page.
The Summary Report
4Check
Runoff and loads (Equations 9-1 and 9-2 of AH Vol I).
| Runoff | = ROC × area × rainfall / 12 |
| = 0.795 × 1.00 ac × 54.0 in / 12 | |
| = 3.578 ac-ft/yr (program 3.578). |
| TN load | = EMC × runoff × 1.233 |
| = 1.050 × 3.578 × 1.233 | |
| = 4.632 kg/yr (program 4.632) |
| TP load | = 0.120 × 3.578 × 1.233 |
| = 0.529 kg/yr (program 0.529). |
1.233 kg is 1 mg/L in 1 ac-ft.
REV coordinates.
| Equivalent impervious area EIA | = 41,517 sf (roof area × the runoff coefficient of a concrete, 0.2% slope roof). |
| Harvest volume over EIA | = 30,000 gal / 7.4805 gal/cf / 41,517 sf × 12 |
| = 1.1592 in (program 1.1592). |
| Use rate over EIA | = 1.50 in/week × 87,120 sf / 7 / 41,517 sf |
| = 0.4497 in/day (program 0.4497). |
Capture. The rate-efficiency-volume (REV) curves for Florida Zone 3 at those coordinates give 84.62 %; water that is used is not discharged, so TN and TP removal equal it (Harvesting and Greenroof Methodology).
Load out.
| TN out | = load in × (1 − removal) |
| = 4.632 × (1 − 84.62 / 100) | |
| = 0.713 kg/yr (program 0.713) |
| TP out | = 0.529 × (1 − 84.62 / 100) |
| = 0.081 kg/yr (program 0.081). |
The standard is not met, and that is expected. “Redevelopment + OFW” requires 60 % TN and 90 % TP of the post-development load (AH Vol I 8.3.5(b)). The post = pre removal (Equation 9-3, (post load − pre load) / post load) is TN 89.8 % and TP 96.5 %. BMPFast takes the larger of the standard’s percentage and the post = pre removal as the Maximum % Removal, shown on every worksheet’s status bar and in the Summary Report: here TN 60.0 % and TP 90.0 %. This problem shows what this design removes (84.6 % / 84.6 %), which is less. To meet it, add BMPs in series or downstream catchments (see BMPs in Series and Routing), or size the BMP (see Sizing).
The program’s Equations page
5Files
- rainwater-school.bmpt: the project, saved by BMPFast. Save it (your browser puts it in Downloads). In BMPFast press Open Project, then Open Project again in the Open BMPFast Project dialog (below its Recent Projects list), and choose the file.
- Equations page (worksheet) (as BMPFast shows it)
- Summary Report (as BMPFast shows it)
- BMP report (worksheet) (as BMPFast shows it)
6Help and methodology
Calculated with BMPFast 1.1.9 (build 6.0.0, 2026-10-16). Older versions may not have the Equations button or may give slightly different results; download the latest at bmpfast.com. Screen captures are for demonstration only.