Exfiltration trench under a parking lot

A 36-inch pipe in a 300 ft trench; All sites non-exempted, Zone 3.

1The problem

A 2-acre commercial parking lot drains to a 300 ft exfiltration trench with a 36-inch perforated pipe.

InputValueSource
Project (General Site Information)
Meteorological zoneFlorida Zone 3Zone map (help page 815)
Mean annual rainfall54 inMean annual rainfall map (help page 815)
Performance standard (analysis type)All sites non-exemptedSite (illustrative)
Catchment 1: Commercial site (Watershed Characteristics)
Land use, pre / postUndeveloped - Mesic Flatwoods / High-Intensity CommercialSite (illustrative)
Area, pre / post2 / 2 acSite (illustrative)
Non-DCIA curve number, pre / post70 / 80Site (illustrative)
DCIA, pre / post0 / 70 %Site (illustrative)
EMC TN, pre / post1.087 / 2.400 mg/LBMPFast land use table (AH Vol I Table 9.2)
EMC TP, pre / post0.043 / 0.345 mg/LBMPFast land use table (AH Vol I Table 9.2)
Exfiltration Systems (worksheet)
Pipe Span36 inDesign (illustrative)
Pipe Rise36 inDesign (illustrative)
Pipe Length300 ftDesign (illustrative)
Trench/Vault Width6 ftDesign (illustrative)
Trench/Vault Depth5 ftDesign (illustrative)
Trench/Vault Length300 ftDesign (illustrative)
Void space fraction not in pipe0.4Design (illustrative)
Time to recover design volume72 hrDesign (illustrative)

Find: the TN and TP removal of the BMP, the loads leaving the site, and whether the performance standard is met.

2Steps in BMPFast 2

  1. Start BMPFast 2 and choose File ▸ New project. The tree on the left opens on the project (General Site Information). On its Entry tab enter: Project name Exfiltration trench: commercial site; Meteorological zone Florida Zone 3; Mean annual rainfall 54.00 in; Type of analysis All sites non-exempted. (To follow along with the finished project instead, choose File ▸ Open and open exfiltration-trench.bmpf from Files below.)

    General Site Information: the project’s Entry tab.
    General Site Information: the project’s Entry tab.
  2. Press Add Catchment (left). Select the new catchment in the tree; on its Entry tab type the name Commercial site and enter: Land use (pre) Undeveloped - Mesic Flatwoods; Land use (post) High-Intensity Commercial; Area (pre) 2.00 ac; Area (post) 2.00 ac; Non-DCIA curve number (pre) 70.00; Non-DCIA curve number (post) 80.00; DCIA (post) 70.00 %. Leave the other boxes as they are (0 or blank). BMPFast 2 calculates as you type; scroll down to Calculated for the results after development: Annual runoff coefficient (ROC) (post) 0.596; Runoff volume (post) 5.364 ac-ft/yr; Nitrogen load (post) 15.873 kg/yr; Phosphorus load (post) 2.282 kg/yr.

    The catchment Commercial site: its Entry tab.
    The catchment Commercial site: its Entry tab.
  3. With Commercial site selected, press Add Treatment and choose Exfiltration. On its Entry tab type the Treatment name Exfiltration (BMPFast 2 starts it as “Exfiltration 1”) and enter: Pipe span 36.00 in; Pipe rise 36.00 in; Pipe length 300.00 ft; Trench/vault width 6.00 ft; Trench/vault depth 5.00 ft; Trench/vault length 300.00 ft; Void space fraction not in pipe 0.40; Design volume removal takes more than 3 hours Yes; Time to recover the design volume 72.00 hr. The results are calculated as you type: Pipe volume 2,120.58 ft³; Trench/vault volume 2,751.77 ft³; Treatment volume 0.112 ac-ft; Treatment depth 0.671 in; Nitrogen removal provided 59.61 %; Phosphorus removal provided 59.61 %.

    The treatment Exfiltration: its Entry tab.
    The treatment Exfiltration: its Entry tab.
  4. Open the treatment’s Report tab: its inputs and removal, as a report to print or save.

    The treatment Exfiltration: its Report tab.
    The treatment Exfiltration: its Report tab.
  5. Press Add Routing (left). BMPFast 2 adds Routing 1 under Catchment Routings, with every catchment draining to the outlet and no treatment; a project can have several routings, compared side by side. On its Entry tab (How the routing is calculated Strand routing (v1's routing; use this for permits)) set each catchment as in this table:

    CatchmentDrains toTreatment used
    Commercial siteOutletExfiltration

    A catchment is treated only by the treatment its routing uses.

    The routing’s Entry tab: where each catchment drains and the treatment it uses.
    The routing’s Entry tab: where each catchment drains and the treatment it uses.
  6. Open the routing’s Report tab. Results shows the loads leaving the site, the removal provided and required, and whether the performance standard is met; the list at the top of the tab has v1’s reports for the same routing (Summary, Complete, Flow Balance, AH Vol I Sec 9 compliance). Save the project with File ▸ Save; compare it with the .bmpf under Files.

    The routing’s Report tab: Results.
    The routing’s Report tab: Results.

3Results

ResultValue
Catchment 1: computed by BMPFast
Annual runoff coefficient (ROC), pre / post0.078 / 0.596
Runoff, pre / post0.702 / 5.364 ac-ft/yr
TN load, pre / post0.941 / 15.873 kg/yr
TP load, pre / post0.037 / 2.282 kg/yr
Exfiltration: computed by BMPFast
Treatment depth0.671 in
Hydraulic capture efficiency59.61 %
Provided TN / TP removal59.61 % / 59.61 %
TN load in → out15.873 → 6.411 kg/yr
TP load in → out2.282 → 0.922 kg/yr
Site (all catchments, at the outlet)
TN load: catchments → outlet15.873 → 6.411 kg/yr
TP load: catchments → outlet2.282 → 0.922 kg/yr
Provided removal TN / TP59.6 % / 59.6 %
Required removal TN / TP (Maximum % Removal)94.1 % (not met) / 98.4 % (not met)

The BMP report

Open this report on its own page.

The Summary Report

Open this report on its own page.

BMPFast 2 and BMPFast (v1)

ResultBMPFast 2BMPFast (v1), its page
Nitrogen leaving the site6.411 kg/yr6.411 kg/yrsame
Phosphorus leaving the site0.922 kg/yr0.922 kg/yrsame
Site removal, nitrogen59.609 %59.609 %same
Site removal, phosphorus59.609 %59.609 %same
Commercial site: Exfiltration removal, nitrogen59.609 %59.609 %same
Commercial site: Exfiltration removal, phosphorus59.609 %59.609 %same

Every number BMPFast 2 gives for this problem is the same as BMPFast (v1)’s, to three decimals.

4Check

Runoff and loads (Equations 9-1 and 9-2 of AH Vol I).

1.233 kg is 1 mg/L in 1 ac-ft.

Storage.

Treatment depth.

Capture. The retention efficiency tables for Florida Zone 3 at a treatment depth of 0.671 in, non-DCIA CN 80.00 and DCIA 70.0 % give a hydraulic capture of 59.61 % (AH Vol I Appendix O; read the same tables with Calculators ▸ Retention Efficiency Tables, help page 4325). An exfiltration system is a retention BMP: the removal equals the capture.

Load out.

The standard is not met, and that is expected. “All sites non-exempted” requires the greater of 55 % TN and 80 % TP, or the removal that keeps the post-development load at the pre-development load (Equation 9-3) (AH Vol I 8.3.2). The post = pre removal (Equation 9-3, (post load − pre load) / post load) is TN 94.1 % and TP 98.4 %. BMPFast takes the larger of the standard’s percentage and the post = pre removal as the Maximum % Removal, shown on every worksheet’s status bar and in the Summary Report: here TN 94.1 % and TP 98.4 %. This problem shows what this design removes (59.6 % / 59.6 %), which is less. To meet it, add BMPs in series or downstream catchments (see BMPs in Series and Routing), or size the BMP (see Sizing).

The program’s Equations page

Open this report on its own page.

5Files

  • exfiltration-trench.bmpf: the project, saved by BMPFast 2. Save it (your browser puts it in Downloads), then in BMPFast 2 choose File ▸ Open and open it. Opened again and calculated, it gives the numbers on this page.
  • exfiltration-trench.bmpt: the same project as BMPFast (v1) saved it. BMPFast 2 opens it too (File ▸ Open); saving it then makes a .bmpf and leaves the .bmpt as it was.
  • Routing 1 (BMPFast 2’s report, as Open in browser on its Report tab gives it)
  • Routing 1 — Summary Report (BMPFast 2’s report, as Open in browser on its Report tab gives it)
  • Exfiltration (BMPFast 2’s report, as Open in browser on its Report tab gives it)
  • Exfiltration — calculations (BMPFast 2’s report, as Open in browser on its Report tab gives it)

6Help and methodology

Calculated with BMPFast 2 version 2.0.0 (2026-10-20), which opens the problem’s v1 project as it is. Screen captures are of BMPFast 2’s own window and are for demonstration only.