All programs › BMPFast › BMPFast 2 sample problems
Roadside swale with swale blocks
A 1,000 ft swale with 8 blocks along a two-lane road; Redevelopment + OFW, Zone 2.
Help: Swale (help page 324) · Download the .bmpf · Link to Solution in BMPFast Version 1
1The problem
A two-lane road (36 ft of pavement and shoulders, 1,000 ft long) drains to a 1,000 ft roadside swale with eight swale blocks 0.5 ft high.
| Input | Value | Source |
|---|---|---|
| Project (General Site Information) | ||
| Meteorological zone | Florida Zone 2 | Zone map (help page 815) |
| Mean annual rainfall | 50 in | Mean annual rainfall map (help page 815) |
| Performance standard (analysis type) | Redevelopment + OFW | Site (illustrative) |
| Catchment 1: Road and shoulders (Watershed Characteristics) | ||
| Land use, pre / post | Undeveloped - Mesic Flatwoods / Highway | Site (illustrative) |
| Area, pre / post | 2.75 / 2.75 ac | Site (illustrative) |
| Non-DCIA curve number, pre / post | 70 / 80 | Site (illustrative) |
| DCIA, pre / post | 0 / 45 % | Site (illustrative) |
| EMC TN, pre / post | 1.087 / 1.250 mg/L | BMPFast land use table (AH Vol I Table 9.2) |
| EMC TP, pre / post | 0.043 / 0.173 mg/L | BMPFast land use table (AH Vol I Table 9.2) |
| Swale (worksheet) | ||
| Swale top width for flood conditions [W] | 20 ft | Design (illustrative) |
| Swale bottom width [B] | 4 ft | Design (illustrative) |
| Swale length [L] | 1000 ft | Design (illustrative) |
| Average catchment length | 1000 ft | Design (illustrative) |
| Average impervious width (including shoulder) | 36 ft | Design (illustrative) |
| Average width of pervious area including swale | 84 ft | Design (illustrative) |
| Swale slope [S] | 0.005 ft/ft | Design (illustrative) |
| Manning's n | 0.2 | Design (illustrative) |
| Soil infiltration rate | 2.0 in/hr | Design (illustrative) |
| Side slope [Z] | 4 H:V | Design (illustrative) |
| Average height of the swale blocks [H] | 0.5 ft | Design (illustrative) |
| Length of the berm upstream of the crest | 10 ft | Design (illustrative) |
| Number of swale blocks | 8 | Design (illustrative) |
Find: the TN and TP removal of the BMP, the loads leaving the site, and whether the performance standard is met.
2Steps in BMPFast 2
Start BMPFast 2 and choose File ▸ New project. The tree on the left opens on the project (General Site Information). On its Entry tab enter: Project name Swale with blocks: two-lane road; Meteorological zone Florida Zone 2; Mean annual rainfall 50.00 in; Type of analysis Redevelopment + OFW. (To follow along with the finished project instead, choose File ▸ Open and open
swale-blocks.bmpffrom Files below.)
General Site Information: the project’s Entry tab. Press Add Catchment (left). Select the new catchment in the tree; on its Entry tab type the name Road and shoulders and enter: Land use (pre) Undeveloped - Mesic Flatwoods; Land use (post) Highway; Area (pre) 2.75 ac; Area (post) 2.75 ac; Non-DCIA curve number (pre) 70.00; Non-DCIA curve number (post) 80.00; DCIA (post) 45.00 %. Leave the other boxes as they are (0 or blank). BMPFast 2 calculates as you type; scroll down to Calculated for the results after development: Annual runoff coefficient (ROC) (post) 0.425; Runoff volume (post) 4.870 ac-ft/yr; Nitrogen load (post) 7.506 kg/yr; Phosphorus load (post) 1.039 kg/yr.

The catchment Road and shoulders: its Entry tab. With Road and shoulders selected, press Add Treatment and choose Swale. On its Entry tab type the Treatment name Swale (BMPFast 2 starts it as “Swale 1”) and enter: Top width for flood conditions [W] 20.00 ft; Bottom width [B] 4.00 ft; Length [L] 1,000.00 ft; Slope [S] 0.0050 ft/ft; Side slope [Z] 4.00 H:V; Manning's n 0.200; Soil infiltration rate 2.00 in/hr; Average height of the swale blocks [H] 0.50 ft; Length of the berm upstream of the crest 10.00 ft; Number of swale blocks 8; Average impervious width (including shoulder) 36.00 ft; Average catchment length 1,000.00 ft; Average pervious width (including the swale) 84.00 ft. The results are calculated as you type: Swale catchment area used 2.75 ac; Rainfall excess area 1.286 ac; Retention volume 0.050 ac-ft; Treatment depth 0.466 in; Nitrogen removal provided 59.67 %; Phosphorus removal provided 59.67 %.

The treatment Swale: its Entry tab. Open the treatment’s Report tab: its inputs and removal, as a report to print or save.

The treatment Swale: its Report tab. Press Add Routing (left). BMPFast 2 adds Routing 1 under Catchment Routings, with every catchment draining to the outlet and no treatment; a project can have several routings, compared side by side. On its Entry tab (How the routing is calculated Strand routing (v1's routing; use this for permits)) set each catchment as in this table:
Catchment Drains to Treatment used Road and shoulders Outlet Swale A catchment is treated only by the treatment its routing uses.

The routing’s Entry tab: where each catchment drains and the treatment it uses. Open the routing’s Report tab. Results shows the loads leaving the site, the removal provided and required, and whether the performance standard is met; the list at the top of the tab has v1’s reports for the same routing (Summary, Complete, Flow Balance, AH Vol I Sec 9 compliance). Save the project with File ▸ Save; compare it with the .bmpf under Files.

The routing’s Report tab: Results.
3Results
| Result | Value |
|---|---|
| Catchment 1: computed by BMPFast | |
| Annual runoff coefficient (ROC), pre / post | 0.057 / 0.425 |
| Runoff, pre / post | 0.653 / 4.870 ac-ft/yr |
| TN load, pre / post | 0.875 / 7.506 kg/yr |
| TP load, pre / post | 0.035 / 1.039 kg/yr |
| Swale: computed by BMPFast | |
| Treatment depth | 0.466 in |
| Hydraulic capture efficiency | 59.67 % |
| Provided TN / TP removal | 59.67 % / 59.67 % |
| TN load in → out | 7.506 → 3.027 kg/yr |
| TP load in → out | 1.039 → 0.419 kg/yr |
| Site (all catchments, at the outlet) | |
| TN load: catchments → outlet | 7.506 → 3.027 kg/yr |
| TP load: catchments → outlet | 1.039 → 0.419 kg/yr |
| Provided removal TN / TP | 59.7 % / 59.7 % |
| Required removal TN / TP (Maximum % Removal) | 60.0 % (not met) / 90.0 % (not met) |
The BMP report
Open this report on its own page.
The Summary Report
Open this report on its own page.
BMPFast 2 and BMPFast (v1)
| Result | BMPFast 2 | BMPFast (v1), its page | |
|---|---|---|---|
| Nitrogen leaving the site | 3.027 kg/yr | 3.027 kg/yr | same |
| Phosphorus leaving the site | 0.419 kg/yr | 0.419 kg/yr | same |
| Site removal, nitrogen | 59.670 % | 59.670 % | same |
| Site removal, phosphorus | 59.670 % | 59.670 % | same |
| Road and shoulders: Swale removal, nitrogen | 59.670 % | 59.670 % | same |
| Road and shoulders: Swale removal, phosphorus | 59.670 % | 59.670 % | same |
Every number BMPFast 2 gives for this problem is the same as BMPFast (v1)’s, to three decimals.
4Check
Runoff and loads (Equations 9-1 and 9-2 of AH Vol I).
| Runoff | = ROC × area × rainfall / 12 |
| = 0.425 × 2.75 ac × 50.0 in / 12 | |
| = 4.870 ac-ft/yr (program 4.870). |
| TN load | = EMC × runoff × 1.233 |
| = 1.250 × 4.870 × 1.233 | |
| = 7.506 kg/yr (program 7.506) |
| TP load | = 0.173 × 4.870 × 1.233 |
| = 1.039 kg/yr (program 1.039). |
1.233 kg is 1 mg/L in 1 ac-ft.
| Rainfall excess area | = (W × L + impervious L × impervious W) / 43,560 |
| = (20 × 1,000 + 1,000 × 36) / 43,560 | |
| = 1.2856 ac (program 1.2856). |
Swale blocks.
| w | = B + 2ZH |
| = 8.00 ft |
| sl | = min(H/S, L/Nb) |
| = 100.0 ft |
| storage | = (w × H / 6) × (sl − Lb) × Nb |
| = 480.0 cf, 0.1029 in over the rainfall excess area. |
With the infiltrated depth of 0.3633 in the treatment depth is 0.4661 in (program 0.4661).
Capture. The retention efficiency tables for Florida Zone 2 at a treatment depth of 0.466 in, non-DCIA CN 80.00 and DCIA 45.0 % give a hydraulic capture of 59.67 % (AH Vol I Appendix O; read the same tables with Calculators ▸ Retention Efficiency Tables, help page 4325). A swale is a retention BMP: the removal equals the capture.
Load out.
| TN out | = load in × (1 − removal) |
| = 7.506 × (1 − 59.67 / 100) | |
| = 3.027 kg/yr (program 3.027) |
| TP out | = 1.039 × (1 − 59.67 / 100) |
| = 0.419 kg/yr (program 0.419). |
The standard is not met, and that is expected. “Redevelopment + OFW” requires 60 % TN and 90 % TP of the post-development load (AH Vol I 8.3.5(b)). The post = pre removal (Equation 9-3, (post load − pre load) / post load) is TN 88.3 % and TP 96.7 %. BMPFast takes the larger of the standard’s percentage and the post = pre removal as the Maximum % Removal, shown on every worksheet’s status bar and in the Summary Report: here TN 60.0 % and TP 90.0 %. This problem shows what this design removes (59.7 % / 59.7 %), which is less. To meet it, add BMPs in series or downstream catchments (see BMPs in Series and Routing), or size the BMP (see Sizing).
The program’s Equations page
5Files
- swale-blocks.bmpf: the project, saved by BMPFast 2. Save it (your browser puts it in Downloads), then in BMPFast 2 choose File ▸ Open and open it. Opened again and calculated, it gives the numbers on this page.
- swale-blocks.bmpt: the same project as BMPFast (v1) saved it. BMPFast 2 opens it too (File ▸ Open); saving it then makes a .bmpf and leaves the .bmpt as it was.
- Routing 1 (BMPFast 2’s report, as Open in browser on its Report tab gives it)
- Routing 1 — Summary Report (BMPFast 2’s report, as Open in browser on its Report tab gives it)
- Swale (BMPFast 2’s report, as Open in browser on its Report tab gives it)
- Swale — calculations (BMPFast 2’s report, as Open in browser on its Report tab gives it)
6Help and methodology
Calculated with BMPFast 2 version 2.0.0 (2026-10-20), which opens the problem’s v1 project as it is. Screen captures are of BMPFast 2’s own window and are for demonstration only.