Composite EMC: phosphorus before development
Pasture, citrus and wet flatwoods on a 40-acre farm.
Help: Composite EMCs (help page 819) · Download the .bmpt · Link to Solution in BMPFast Version 2
1The problem
Before development a 40-acre farm is 25 ac pasture (TP 0.593 mg/L, CN 69), 10 ac citrus (0.18, CN 60) and 5 ac wet flatwoods (0.021, CN 70).
| Input | Value | Source |
|---|---|---|
| Project (General Site Information) | ||
| Meteorological zone | Florida Zone 4 | Zone map (help page 815) |
| Mean annual rainfall | 52 in | Mean annual rainfall map (help page 815) |
| Performance standard (analysis type) | All sites non-exempted | Site (illustrative) |
| Catchment 1: Farm (Watershed Characteristics) | ||
| Land use, pre / post | User Defined Values / Single-Family | Site (illustrative) |
| Area, pre / post | 40 / 40 ac | Site (illustrative) |
| Non-DCIA curve number, pre / post | 65 / 75 | Site (illustrative) |
| DCIA, pre / post | 0 / 25 % | Site (illustrative) |
| EMC TN, pre / post | 2.500 / 1.770 mg/L | BMPFast land use table (AH Vol I Table 9.2) |
| EMC TP, pre / post | 0.442 / 0.327 mg/L | BMPFast land use table (AH Vol I Table 9.2) |
| Parts of the catchment | ||
| 25 ac | EMC 0.593 mg/L, CN 69 | Land use table (AH Vol I Table 9.2) |
| 10 ac | EMC 0.18 mg/L, CN 60 | Land use table (AH Vol I Table 9.2) |
| 5 ac | EMC 0.021 mg/L, CN 70 | Land use table (AH Vol I Table 9.2) |
Find: the composite TP EMC and the load it gives.
2Steps in BMPFast
On 1. Enter Catchment press ?/+ beside the TP EMC to open the Composite EMC calculator. Type each part’s area, EMC and CN and press Calculate. Press Back and answer Yes to use it.

The Composite EMC calculator (TP) after Calculate. The catchment with the composite EMC, after Calculate. Press Save Project to keep your copy; compare it with the .bmpt under Files.

Watershed Characteristics Worksheet (1. Enter Catchment).
3Results
| Result | Value |
|---|---|
| Composite TP EMC | 0.442 mg/L |
| TN load, pre / post | 28.852 / 104.785 kg/yr |
| TP load, pre / post | 5.101 / 19.359 kg/yr |
4Check
Method.
The composite EMC is weighted by runoff, not by area: each part’s weight is its area × its annual runoff coefficient (the C × A column).
| EMC | = (0.593 × 0.042 + 0.18 × 0.010 + 0.021 × 0.009) / 0.061 |
| = 0.441 mg/L (program 0.442). |
A part with more runoff counts for more (AH Vol I 9.2.2 a; help page 819).
5Files
- composite-emc-phosphorus.bmpt: the project, saved by BMPFast. Save it (your browser puts it in Downloads). In BMPFast press Open Project, then Open Project again in the Open BMPFast Project dialog (below its Recent Projects list), and choose the file.
- Summary Report (as BMPFast shows it)
- BMP report (worksheet) (as BMPFast shows it)
6Help and methodology
Calculated with BMPFast 1.1.9 (build 6.0.0, 2026-10-16). Older versions may not have the Equations button or may give slightly different results; download the latest at bmpfast.com. Screen captures are for demonstration only.