Greenroof with a cistern for irrigation

One acre of greenroof with 2 in of cistern storage, Miami; Redevelopment + Impaired.

1The problem

A 1-acre hotel roof in Miami is a greenroof whose filtrate goes to a cistern of 2 in over the roof; the water irrigates the roof (20 in/yr).

InputValueSource
Project (General Site Information)
Meteorological zoneFlorida Zone 5Zone map (help page 815)
Mean annual rainfall60 inMean annual rainfall map (help page 815)
Performance standard (analysis type)Redevelopment + ImpairedSite (illustrative)
Catchment 1: Hotel roof (Watershed Characteristics)
Land use, pre / postUndeveloped - Mesic Flatwoods / Conventional RoofsSite (illustrative)
Area, pre / post1 / 1 acSite (illustrative)
Non-DCIA curve number, pre / post70 / 98Site (illustrative)
DCIA, pre / post0 / 100 %Site (illustrative)
EMC TN, pre / post1.087 / 1.050 mg/LBMPFast land use table (AH Vol I Table 9.2)
EMC TP, pre / post0.043 / 0.120 mg/LBMPFast land use table (AH Vol I Table 9.2)
Greenroof (worksheet)
Rainfall stationMiami #5663Design (illustrative)
Greenroof area43560 sfDesign (illustrative)
Cistern storage over greenroof area2.0 inDesign (illustrative)
Irrigation demand20 in/yrDesign (illustrative)
Rainfall excess (filtrate underdrain flow)0 in/yrDesign (illustrative)

Find: the TN and TP removal of the BMP, the loads leaving the site, and whether the performance standard is met.

2Steps in BMPFast

  1. Press New Project. On General Site Information (the main window; its title bar reads General Site Information and your license key) type the project name Greenroof: with cistern for irrigation, choose Florida Zone 5, enter 60 in of mean annual rainfall and choose the performance standard Redevelopment + Impaired.

    General Site Information (the main window).
    General Site Information (the main window).
  2. Press 1. Enter Catchment. For Catchment 1 type the name Hotel roof, choose the land uses Undeveloped - Mesic Flatwoods (pre) and Conventional Roofs (post), enter the areas 1 and 1 ac, the non-DCIA curve numbers 70 and 98 and the DCIA 0 and 100 %, then press Calculate. BMPFast shows the annual runoff coefficient, the runoff and the TN and TP loads. Press Back.

    Watershed Characteristics Worksheet (1. Enter Catchment).
    Watershed Characteristics Worksheet (1. Enter Catchment).
  3. Press 2. Enter Treatment and then Greenroof. On the Greenroof worksheet: Rainfall station Miami #5663; Greenroof area 43560 sf; Cistern storage over greenroof area 2.0 in; Irrigation demand 20 in/yr; Rainfall excess (filtrate underdrain flow) 0 in/yr. Press Calculate. The report on the worksheet shows the inputs and the results.

    The BMP worksheet after Calculate: the report on the left.
    The BMP worksheet after Calculate: the report on the left.
  4. Press the same button again, now labelled Equations: the worksheet shows each equation with this problem’s values. Press Back to return to the treatment options.

    The same worksheet showing Equations: each equation with this problem’s values.
    The same worksheet showing Equations: each equation with this problem’s values.
  5. On the main window press 3. Configure Catchments and double-click Catchment 1. Choose Greenroof as the BMP used in routing and the Outlet as where it goes. Press Back twice. (A catchment’s BMP is only used once it is chosen here.)

    Routing for Catchment 1 (3. Configure Catchments): the BMP used and where the catchment goes.
    Routing for Catchment 1 (3. Configure Catchments): the BMP used and where the catchment goes.
  6. Press 4. Summary Report. The Report Viewer shows the loads, the removal and whether the performance standard is met. Press Save Project to keep your copy; compare it with the .bmpt under Files.

    The Summary Report (4. Summary Report) in the Report Viewer.
    The Summary Report (4. Summary Report) in the Report Viewer.

3Results

ResultValue
Catchment 1: computed by BMPFast
Annual runoff coefficient (ROC), pre / post0.093 / 0.808
Runoff, pre / post0.465 / 4.040 ac-ft/yr
TN load, pre / post0.623 / 5.230 kg/yr
TP load, pre / post0.025 / 0.598 kg/yr
Greenroof: computed by BMPFast
Treatment depth2.000 in
Hydraulic capture efficiency69.10 %
Provided TN / TP removal69.10 % / 69.10 %
TN load in → out5.230 → 1.616 kg/yr
TP load in → out0.598 → 0.185 kg/yr
Site (all catchments, at the outlet)
TN load: catchments → outlet5.230 → 1.616 kg/yr
TP load: catchments → outlet0.598 → 0.185 kg/yr
Provided removal TN / TP69.1 % / 69.1 %
Required removal TN / TP (Maximum % Removal)88.1 % (not met) / 95.9 % (not met)

The BMP report

Open this report on its own page.

The Summary Report

Open this report on its own page.

4Check

Runoff and loads (Equations 9-1 and 9-2 of AH Vol I).

1.233 kg is 1 mg/L in 1 ac-ft.

Capture. With 2.00 in of cistern storage over the roof and 20 in/yr of irrigation demand, the greenroof tables for Miami #5663 give 69.10 %. The water that stays on the roof keeps its nitrogen and phosphorus, so the TN and TP removal equal the capture (Harvesting and Greenroof Methodology).

Load out.

The standard is not met, and that is expected. “Redevelopment + Impaired” requires the redevelopment percentages, 45 % TN and 80 % TP, together with the pre/post comparison (AH Vol I 8.3.5(c)). The post = pre removal (Equation 9-3, (post load − pre load) / post load) is TN 88.1 % and TP 95.9 %. BMPFast takes the larger of the standard’s percentage and the post = pre removal as the Maximum % Removal, shown on every worksheet’s status bar and in the Summary Report: here TN 88.1 % and TP 95.9 %. This problem shows what this design removes (69.1 % / 69.1 %), which is less. To meet it, add BMPs in series or downstream catchments (see BMPs in Series and Routing), or size the BMP (see Sizing).

The program’s Equations page

Open this report on its own page.

5Files

6Help and methodology

Calculated with BMPFast 1.1.9 (build 6.0.0, 2026-10-16). Older versions may not have the Equations button or may give slightly different results; download the latest at bmpfast.com. Screen captures are for demonstration only.