Composite EMCs

A copy of the help on bmpfast.com (last changed there 2026-10-20; copied here 2026-10-21). These pages describe the windows of BMPFast (version 1). BMPFast 2 uses the same methods; its numbered buttons are the tree on the left: General Site Information, then Catchments with their Treatments, Catchment Routings and Calculators.

The Composite EMC calculator works out a single event mean concentration (EMC) of total nitrogen or total phosphorus for a catchment that contains several land uses. Each land use is weighted by the average annual runoff it produces (its area times its annual runoff coefficient), not by area alone, because the load that reaches a BMP depends on how much water each part sends.

To open it, choose User Defined Values as the Pre or Post land use on the Watershed Characteristics Worksheet. A + button then appears beside each EMC box of that condition: one for EMC(N) and one for EMC(P). The window title ends with the condition and nutrient, e.g. “Post-Development Total Nitrogen”.

How to use it

  1. Set the DCIA percentage for the condition on the worksheet first; the calculator uses it (shown as DCIA Percent).
  2. Enter one row per land use: Area (ac), its EMC (mg/L) for the nutrient named in the title, and its CN. As the window title says, include all the pervious and the DCIA area; give DCIA a CN of 95. Up to 20 rows.
  3. Press Calculate.
  4. Press Back, then answer Yes to put the Composite EMC into the worksheet’s EMC box (rounded to 3 decimals).
  5. Repeat with the other + button for the other nutrient. The Area and CN rows are already there; enter that nutrient’s EMCs.

Inputs

InputUnitsWhat it means / how it is used
Area (ac)acArea of this land use within the catchment.
EMCmg/LEvent mean concentration of the nutrient named in the window title (Total Nitrogen or Total Phosphorus) for this land use. The land-use EMCs listed on the Catchment Characteristics page can be used.
CNCNCurve number of this land use; 95 for DCIA. Kept with 2 decimals, as in the Composite CN calculator, which shares these rows: Curve Numbers are typically rounded to the nearest integer; 2 decimal places are used here for computational accuracy.

Results

ResultUnitsMeaning
C (grey column)0–1Annual runoff coefficient of the row, read from the ROC table for the project’s rainfall zone at the row’s CN and the catchment’s DCIA percentage.
Weighted C (grey column)0–1The row’s C times its share of the total area entered.
Avg Weighted C0–1Sum of the Weighted C column.
DCIA Percent%The catchment’s DCIA percentage for this condition (from the worksheet; not editable here).
Composite EMCmg/LThe runoff-weighted EMC (below).

Method

C_i           = ROC table(rainfall zone, CN_i, DCIA %)
Composite EMC = Σ (EMC_i × C_i × A_i) / Σ (C_i × A_i)

C_i × A_i is proportional to the average annual runoff from each land use, so each EMC counts in proportion to the water it contributes. A row with no CN gets no runoff and does not count.

Applicant’s Handbook reference

Section 9.2.2 Calculating Predevelopment and Post-development Stormwater Nutrient Loading, paragraphs a and c (Table 9.2, Equation 9-2): each land use’s load is its annual runoff volume times its EMC; a runoff-weighted EMC gives the same total load as adding the land uses’ loads, so this calculator follows the handbook. Use Table 9.2 EMCs, or study EMCs under paragraph b.

Source reference

Harper, H.H. and Baker, D.M. (2007). Evaluation of Current Stormwater Design Criteria within the State of Florida. Final report, FDEP Contract S0108, Appendix C (Calculated Annual Runoff Coefficients for the Designated Meteorological Zones as a Function of Curve Number and DCIA) and Section 4.2.1 (link): the annual runoff coefficient (ROC) tables were made by continuous simulation with the SCS curve number method, runoff from DCIA starting after 0.1 in of rain; BMPFast reads these tables for every catchment, and Appendix N of the handbook reproduces them.

BMPFast method (frmCompositeEMC): weighting each land use’s EMC by its runoff, C × A, is BMPFast’s way of combining land uses into one EMC.

Buttons

ButtonWhat it does
CalculateStores the rows with the catchment and recalculates.
BackStores the rows, recalculates, and asks “Do you want to use this value as the Event Mean Concentration?”. Yes writes the Composite EMC into the worksheet’s EMC box; No leaves it unchanged. The calculator then closes. If the Composite EMC is 0 (no row has a CN), it is not offered: a message asks you to enter a CN for each row, and the calculator stays open (Cancel leaves without changing the EMC). Its tooltip: “Saves the values to this catchment and returns to Catchment Characteristics (you are asked whether to use the result)”; the Composite CN calculator’s button has the same name.
CancelCloses without storing the grid. (Rows already stored by Calculate stay with the catchment.)
CopyCopies the grid (headings and every row with an area) to the clipboard as tab-separated text for a spreadsheet.
PastePastes tab-separated rows from a spreadsheet into the grid, starting at the first row and the Area column; the columns must be in the order Area, EMC, CN. Press Calculate afterwards.
HelpOpens this page.

Notes

  • Shared rows: the Area and CN rows are shared by the nitrogen and phosphorus calculators of the same condition and by the Composite CN Calculator. Only the EMC column is kept separately for N and for P.
  • Enter numbers only in the grid. Leave unused rows at 0 (a blank cell counts as 0). If a cell holds anything else, such as a heading pasted with the data, Calculate and Back say which cell (for example “Row 3, column EMC is not a number”), select it, and do nothing else until it is corrected. Paste skips a first line with no number in it, so a heading copied with the data is left out.
  • After returning, press Calculate on the worksheet so the loads use the new EMC.

Impervious area that is not directly connected: curve number 95 to 98, the designer’s choice (Ron Eaglin, October 19, 2026). Harper and Baker (2007), Section 4.2.1, page 4-28, the source of BMPFast’s runoff tables, use 98; BMPFast’s calculator titles say 95. A higher value gives more runoff and a higher post-development load: say which you used.

Sample problems

Worked problems solved in BMPFast, each with every input, the steps with screen captures, the program’s results, a hand check and the project file to download. Captures are for demonstration only. All of them: BMPFast sample problems.