SoftwarePlus.ai

All programs › BMPFast › Sample problems

Cost analysis: a retention basin

Example Problem 3’s basin: the worked example of the Cost Analysis Methodology.

1The problem

The BMPFast sample project Example Problem 3: the retention basin ($100,000 – $150,000, 20-year life, O&M 1.0 – 6.0 %), its fixed outlet structure ($10,000 – $15,000, 60 years) and mowing twice a year. Discount rate 3.3 %, 30 years, inflation 2.5 %.

InputValueSource
Project (General Site Information)
Meteorological zoneFlorida Zone 4Zone map (help page 815)
Mean annual rainfall50 inMean annual rainfall map (help page 815)
Performance standard (analysis type)Specified Removal EfficiencyBMPFast sample project
Specified removal: TN / TP75 % / 75 %BMPFast sample project
Cost analysis
Discount rate3.3 %Cost analysis parameters
Duration30 yearsCost analysis parameters
BMP inflation rate2.5 %Cost analysis parameters

Find: the present worth, the annual cost and the cost per pound of TN and TP removed.

2Steps in BMPFast

  1. Press 6. Cost Analysis. The hub lists every catchment’s BMP; set the discount rate and duration in A.

    The Cost Analysis hub (6. Cost Analysis).
    The Cost Analysis hub (6. Cost Analysis).
  2. Double-click the Retention row. In B enter the components (construction low and high, life, O&M %), in C the routine costs, in D the energy; press Calculate.

    Cost analysis of one BMP: A parameters and B components.
    Cost analysis of one BMP: A parameters and B components.
  3. Collapse B and open C: the routine maintenance costs, here with the Stormwater Resale credit where there is one (a negative cost). Open E for the summary: present worth, annual cost and cost per pound (the results below).

    The same window with C open: the routine maintenance costs.
    The same window with C open: the routine maintenance costs.
  4. Back on the hub, Full Cost Report shows the costs of every BMP. Press Save Project to keep your copy; compare it with the .bmpt under Files.

    The Full Cost Report.
    The Full Cost Report.

3Results

Result (low – high)Value
Construction$110,000 – $165,000
Present value of replacements$85,599 – $128,399
Present value of O&M$88,707 – $240,675
Present worth$284,306 – $534,074
Annualized cost$15,073 – $28,315
Cost per lb TN removed$232.87 – $437.45
Cost per lb TP removed$1,260.48 – $2,367.83
TN / TP removed40.70 / 7.52 lb/yr

The component cost report

Open this report on its own page.

Full Cost Report

Open this report on its own page.

4Check

Annualized cost.

5Files

6Help and methodology

Calculated with BMPFast 1.1.9 (build 6.0.0, 2026-10-16). Older versions may not have the Equations button or may give slightly different results; download the latest at bmpfast.com. Screen captures are for demonstration only.