Cost Analysis Methodology

A copy of the help on bmpfast.com (last changed there 2026-10-16; copied here 2026-10-21). These pages describe the windows of BMPFast (version 1). BMPFast 2 uses the same methods; its numbered buttons are the tree on the left: General Site Information, then Catchments with their Treatments, Catchment Routings and Calculators.

BMPFast estimates the life-cycle cost of each BMP: what it costs to build, to replace its parts as they wear out, and to operate and maintain it over the years of the analysis. It adds these up as one present worth (all costs brought to today’s dollars), turns that into an annualized cost, and divides the present worth by the nitrogen and phosphorus the BMP removes over the analysis period to give a cost per pound. Every figure is calculated twice, as a Low and a High estimate. This page explains the calculations; the screens where the costs are entered are described on Cost Analysis.

What the analysis needs

InputWhat it isWhere it comes from
Discount rate (%)The interest rate that brings future costs to today’s dollars (r below).The Cost Analysis screens; one value for the whole project. Default 3.3 %.
Analysis period (years)The number of years the costs are counted over (T below).The Cost Analysis screens; one value for the whole project. Default 20 years.
Inflation rate (%)How fast the cost of a replacement grows until it is bought (i below).Each BMP’s cost worksheet. When it is 0, the discount rate is used.
Cost componentsThe physical parts of the BMP (basin, outlet structure, pump, media…). Each has a construction cost (Low, High), a service life (years), an annual O&M cost as a percentage of its construction cost (Low, High), and a replacement cost in today’s dollars (blank = the construction cost).Picked from the component database, which gives the service life and the O&M percentages; the construction costs are entered for the project.
Routine maintenance costsYearly costs not tied to one component: quantity × cost per unit per year (Low, High). A credit (revenue) is a negative cost: #160 Stormwater Resale, offered only for Stormwater Harvesting, with its quantity taken from the harvested water.Picked from the routine cost database.
Electrical energyYearly energy use (kWh) × the electrical rate ($/kWh). The same in the Low and High estimates.Each BMP’s cost worksheet. The rate starts at $0.115/kWh and can be changed.
Nitrogen and phosphorus removed (lb/yr)Load into the BMP minus load out of it, kg/yr × 2.205.The BMP’s own calculation (its load diagram).

The databases. BMPFast carries a component database (IDs 1 to 18: pump stations, piping, detention, retention, outlet structures, baffle boxes, underdrains, BAM, wetlands, canals, underground storage) and a routine cost database (IDs 100 to 160: canal and STA maintenance, AquaFiber, slope repair, mowing, structure cleaning, stormwater resale), from the FSAEF BMP Life-Cycle Costing Tool (2025). A user can edit both and add entries; the edited lists are kept in %AppData%\BMPFast (capital_costs.json and maintenance_costs.json) and used in place of the built-in ones. When a BMP’s cost worksheet is opened with no components, BMPFast fills in the components typical for its type, with blank construction costs to enter.

Source reference

Florida Stormwater Association Educational Foundation (2025). BMP Life-Cycle Costing Tool (presented by Cunningham, FSA Annual Meeting, June 2024) (link): BMPFast’s cost method, the component (IDs 1 to 18) and routine cost (IDs 100 to 160) databases in WQSystemDatabase.cs, the 3.3 % default discount rate (the long-term CPI average, 1915 to 2015), the $0.115/kWh electrical rate and the Maintenance Guide all follow this tool.

The method

With r the discount rate and i the inflation rate as fractions (3.3 % = 0.033) and T the analysis period in years:

1. Construction

Construction (Low)  = sum of the components' construction costs, Low
Construction (High) = sum of the High costs (a blank High uses the Low)

2. Replacements

A component is replaced at the end of each service life that falls inside the analysis period. A component whose life is equal to or longer than the period is not replaced.

Number of replacements  n = ceiling(T / Life) − 1      (0 when Life ≥ T)
Cost of the k-th replacement when it is bought:
FV(k) = Replacement Cost × (1 + i)^(k × Life)
Today's value of that replacement:
PV(k) = FV(k) / (1 + r)^(k × Life)
PV of Replacement = PV(1) + PV(2) + ... + PV(n), summed over all components

The Replacement Cost is in today’s dollars: the cost of one replacement if it were bought now. Left blank, it is the construction cost. When the inflation rate equals the discount rate (or is left at 0), each replacement’s present value equals today’s replacement cost.

Source reference

BMPFast method (BMP.CalculateComponentCosts; Ron, 2026-10-10): a replacement is priced in today’s dollars, grown at the inflation rate to the year it is bought and discounted back at the discount rate.

3. Operation and maintenance

Annual O&M of a component = Construction Cost × O&M % / 100
Annual routine cost = Quantity × Cost per unit (negative for a credit)
Annual electrical cost = kWh per year × $ per kWh
Present value of an annual cost A over T years:
PV = A × [(1 + r)^T − 1] / [r × (1 + r)^T] (PV = A × T when r = 0)
PV of O&M = the PV of every component's O&M + every routine cost + the electrical cost

A credit, such as stormwater resale, has a negative yearly cost, so it lowers the PV of O&M and the present worth.

4. Present worth, annualized cost and cost per pound

Present Worth   = Construction + PV of Replacement + PV of O&M
Annualized Cost = Present Worth × r × (1 + r)^T / [(1 + r)^T − 1] (Present Worth / T when r = 0)
Cost per lb N = Present Worth / (N removed, lb/yr × T)
Cost per lb P = Present Worth / (P removed, lb/yr × T)

The annualized cost is the steady yearly payment worth the same as the present worth over the analysis period. The cost per pound divides the present worth by all the pounds removed over the period. Each is calculated for the Low and the High estimate.

Which cost per pound. BMPFast uses the present-worth form: Present Worth / (pounds removed per year x T). The present worth is discounted to today and the pounds are not, as in the FSAEF tool’s output. Another common form divides the annualized cost by the pounds removed per year; it gives a higher figure whenever the discount rate is above 0 (in the worked example, $370.38 per pound of N instead of $232.87, about 1.6 times). Compare the same form when comparing BMPFast with another tool. The cost report and the Unit Cost Summary say which form is used, under their tables, and so does the tooltip on $/lb in the Cost Analysis window.

Source reference

BMPFast method (cost per pound; Ron, 2026-10-13): the present-worth form, as in the FSAEF tool’s output, was kept, and the reports say which form they use.

Worked example

A retention basin (the project in Example Problem 3: one catchment, N load in 24.61 kg/yr and out 6.15 kg/yr, P in 4.55 and out 1.14 kg/yr) with a discount rate of 3.3 %, an inflation rate of 2.5 % and a 30-year analysis period:

ItemConstruction (Low / High)LifeO&M % (Low / High)
Retention$100,000 / $150,00020 yr1.0 / 6.0
Outlet Structure, Fixed$10,000 / $15,00060 yr0.03 / 0.4
Mowing / Vegetation Control / Litter Removal (routine)2 × $1,850 per year
StepLowHigh
Construction$110,000$165,000
Replacements: the basin once (n = ceiling(30 / 20) − 1 = 1), at year 20; the outlet none100,000 × 1.02520 = $163,862, today: ÷ 1.03320 = $85,599150,000 → $128,399
Annual O&M1,000 + 3 + 3,700 = $4,703 per year9,000 + 60 + 3,700 = $12,760 per year
PV of O&M (factor [(1.033)30 − 1] / [0.033 × 1.03330] = 18.862)$88,707$240,675
Present Worth$284,306$534,074
Annualized Cost (÷ 18.862)$15,073 per year$28,315 per year
N removed: (24.607 − 6.150) × 2.205 = 40.70 lb/yr; cost per lb N = PW / (40.70 × 30)$232.87$437.45
P removed: (4.546 − 1.136) × 2.205 = 7.52 lb/yr; cost per lb P = PW / (7.52 × 30)$1,260.48$2,367.83

BMPFast gives the same values for these inputs (Present Worth $284,306.02 and $534,074.48).

Notes and limits

  • The costs are per BMP. The Cost Analysis hub lists one row for each BMP (one for each BMP in a Multiple BMP series) and adds them up for the project (Cost Analysis).
  • The pounds removed are the BMP’s own: load in minus load out on its worksheet. How the removal itself is calculated is on Retention Methodology, Retention BMPs and Wet Detention Methodology.
  • The cost per pound uses the present worth over the undiscounted pounds removed in T years.
  • A component with a service life of 1,000 years (detention, canals, land) is never replaced. A BAM component’s life is site-specific (0 in the database) and must be entered; with 0 it is not replaced.
  • The cost database’s values are planning figures. Project costs should replace them where they are known.

Source

The method and the databases follow the Florida Stormwater Association Educational Foundation (FSAEF) BMP Life-Cycle Costing Tool (updated 2025), Florida Stormwater Association (Research), presented by Cunningham at the FSA Annual Meeting, June 2024. The discount rate default, 3.3 %, is the FSAEF recommended default (the long-term average of the consumer price index, 1915-2015).